After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?

A.
Crystal clear development process
Answers
A.
Crystal clear development process
B.
Kanban development process
Answers
B.
Kanban development process
C.
Predictive development process
Answers
C.
Predictive development process
D.
Adaptive development process
Answers
D.
Adaptive development process
Suggested answer: D