A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?

A.
Ensure test scenarios conform to business requirements
Answers
A.
Ensure test scenarios conform to business requirements
B.
Choose an appropriate format to communicate requirements
Answers
B.
Choose an appropriate format to communicate requirements
C.
Analyze requirements to remove unnecessary components
Answers
C.
Analyze requirements to remove unnecessary components
D.
Align business requirements to organizational strategy
Answers
D.
Align business requirements to organizational strategy
Suggested answer: C