Question 513 - CCBA discussion
Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to develop each report based on the business requirements. What should the business analyst (BA) and the stakeholders do with the estimates?
A.
Revise the business requirements
B.
Write functional report specifications
C.
Review the priorities
D.
Analyze technical constraints