Which of the following activities are part of test planning?

I) Setting the entry and exit criteria

II) Determining the validity of bug reports

III) Determining the number of resources required

IV) Determining the expected result for test cases

A.
I . IV
Answers
A.
I . IV
B.
I . III
Answers
B.
I . III
C.
I, III, IV
Answers
C.
I, III, IV
D.
I, II, IV
Answers
D.
I, II, IV
Suggested answer: B

Explanation:

Test planning is a key activity in the testing process that involves defining the objectives, approach, resources, and schedule of intended test activities. Setting the entry and exit criteria (I) and determining the number of resources required (III) are integral parts of test planning. Determining the validity of bug reports (II) is more aligned with test analysis or test management activities post-execution, and determining the expected result for test cases (IV) is part of test design. Therefore, options I and III (B) are the activities that belong to test planning.