Which of the following is an example of tasks most associated with the test design activity?

A.
The project manager updates the project schedule as key test tasks are completed
Answers
A.
The project manager updates the project schedule as key test tasks are completed
B.
Test data, derived from production data, is loaded into the test environment
Answers
B.
Test data, derived from production data, is loaded into the test environment
C.
Every day. the tester notes the status of his/her test cases in preparation for daily reports
Answers
C.
Every day. the tester notes the status of his/her test cases in preparation for daily reports
D.
The identification of test execution and test automation tools
Answers
D.
The identification of test execution and test automation tools
Suggested answer: D

Explanation:

Test design is one of the fundamental activities in software testing, focusing on how tests will be structured and what strategies will be employed. As per the ISTQB syllabus, identifying appropriate test execution and automation tools is a task closely associated with test design activities because it directly influences how tests will be conducted, managed, and executed efficiently. This activity involves deciding on the tools that will best support the testing goals and requirements.

Reference: ISTQB Certified Tester Foundation Level Syllabus v4.0, Section 4.4 'Test Design Techniques'.