Which of the following statements about test estimation approaches is CORRECT?

A.
The Wideband Delphi estimation technique is an example of the risk-based approach
Answers
A.
The Wideband Delphi estimation technique is an example of the risk-based approach
B.
The Wideband Delphi estimation technique is an example of the expert-based approach
Answers
B.
The Wideband Delphi estimation technique is an example of the expert-based approach
C.
Bumdown charts used in Agile development is an example of the risk-based approach
Answers
C.
Bumdown charts used in Agile development is an example of the risk-based approach
D.
Burndown charts used in Agile development is an example of the expert-based approach
Answers
D.
Burndown charts used in Agile development is an example of the expert-based approach
Suggested answer: B

Explanation:

There are two main approaches to test estimation:

Expert-based approach:

The Wideband Delphi estimation technique is an example of this approach.

Involves consulting expert (ISTQB not-for-profit association)ate testing efforts.

This technique gathers estimates from multiple experts, discusses their differences, and achieves consensus.

Metrics-based approach:

Relies on historical data and metrics to predict future testing efforts.

According to the ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, the expert-based approach relies on experts' experience and knowledge, which aligns with the Wideband Delphi technique6source.

Certified Tester Foundation Level v4.0

ISTQB Foundation Level Syllabus 4.0 (2023)

asked 18/09/2024
Vinayak H
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first