Question 195 - CTFL4 discussion
Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:
* most optimistic = 6 person hours
* most likely = 30 person hours
* most pessimistic = 54 person hours
Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?
A.
The final estimate is between 22 person hours and 38 person hours
B.
The final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate
C.
The final estimate is between 6 person hours and 54 person hours
D.
The final estimate is exactly 30 person hours because the technique uses the arithmetic mean of the three initial estimates as the final estimate