During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.

The team agreed on the following:

1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.

2. If estimation values differ significantly, the highest score will be used for estimation purposes.

The result of the first round of planning poker:

Team Member Estimation

Business Large

Development Extra-extra-large

Testing Extra-extra-large

Which of the following options best represent the team's next actions?

A.
The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.
Answers
A.
The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.
B.
The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.
Answers
B.
The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.
C.
Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.
Answers
C.
Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.
D.
the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.
Answers
D.
the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.
Suggested answer: D

Explanation:

In a planning poker session, if there is a significant difference in the estimations, it indicates that there may be misunderstandings or different perspectives on the complexity of the user story. According to the agile principles, the team should discuss these differences to reach a common understanding. The goal is to ensure that all team members have a shared understanding of the user story's scope and complexity before finalizing the estimate.

asked 18/09/2024
Athabile Landzela
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first