You are testing the latest version of an air-traffic control system prior to production deployment using exploratory testing. After following an unusual sequence of input steps, the system crashes. After the crash, you document a defect report with the following information:
* Title: System crashes unexpectedly during input.
* Brief summary: System crashes when an unusual sequence of inputs is used.
* Version: V1.001
* Test: Exploratory testing prior to production deployment
* Priority: Urgent
* Risk: High
*
Reference: Screenshot of crashed application
What critical Information Is missing from this report?
A.
Conclusions, recommendations, and approvals.
B.
Change history.
C.
Description of the defect to enable reproduction.
D.
Status of defect
Your answer:
0 comments