Which of the following best describes the relationship between a test progress report and a test summary report?

A.
The test report prepared during a test activity may be referred to as a test progress report, while a test report prepared at the end of a test activity may be referred to as a test summary report.
Answers
A.
The test report prepared during a test activity may be referred to as a test progress report, while a test report prepared at the end of a test activity may be referred to as a test summary report.
B.
The test report prepared during a test activity may be referred to as a test summary report, while a test report prepared at the end of a test activity may be referred to as a test progress report.
Answers
B.
The test report prepared during a test activity may be referred to as a test summary report, while a test report prepared at the end of a test activity may be referred to as a test progress report.
C.
There is no difference between a test progress report and a test summary report.
Answers
C.
There is no difference between a test progress report and a test summary report.
D.
Both the test progress report and the test summary report should always be generated via an automated tool.
Answers
D.
Both the test progress report and the test summary report should always be generated via an automated tool.
Suggested answer: A

Explanation:

A test progress report is prepared during a test activity and provides updates on the current status of testing activities, including progress made, issues encountered, and test metrics. A test summary report, on the other hand, is prepared at the end of a test activity and provides a comprehensive overview of the testing carried out, including the final status, test results, defect summaries, and overall conclusions.

Reference: ISTQB CTFL Syllabus V4.0, Section 5.3.2

Applicable acceptance test cases for the given user story should focus on the specific requirement of deleting an individual item from the shopping list and ensuring that it is removed in less than 1 second. Therefore, the valid test cases are: i. Click on my online shopping list, select the unwanted item, delete the unwanted item, the unwanted item is deleted from the shopping list in less than 1 second. iii. Tab to the online shopping list and press enter, select the unwanted item, delete the unwanted item, the unwanted item is deleted from the shopping list in less than 1 second.

Reference: ISTQB CTFL Syllabus V4.0, Section 5.2.2