The Salesforce delivery team at Cloud Kicks consistently has user stories that developers start but are unable to complete during each sprint. During the most recent retrospective, the development team expressed that they are running out of time to complete the stories. The team used the INVEST checklist to diagnose why these stories are incomplete at the end of the sprint.

Which checklist item is the most likely reason why the stories are incomplete at the close of the sprint?

A.
Negotiable
Answers
A.
Negotiable
B.
Valuable
Answers
B.
Valuable
C.
Small
Answers
C.
Small
Suggested answer: C

Explanation:

The checklist item that is the most likely reason why the stories are incomplete at the close of the sprint is small. Small means that a user story should be simple and concise, and it should be able to be completed within a single sprint by a single developer or a small team. A user story that is too large or complex may be difficult to estimate, prioritize, test, or deliver within the sprint timeframe. A user story that is too small may be trivial, redundant, or irrelevant to the project goals. A user story that is not small enough may need to be broken down into smaller and more manageable chunks.

Reference: https://trailhead.salesforce.com/content/learn/modules/user-story-creation/write-user-stories