Product A has the 'One per Unit' option selected within the Asset Conversion pteklist. Users era reporting that when they modify the quantity for Product A on on amendment Quote, the following error displays:
'Product cannot be refunded. The quantity of Line # cannot decrease without a corresponding update.'
What should the CPQ specialist do to ensure sales raps can edit the quantity of asset-based products within an amendment Quote?
A.
Set the Asset Amendment Behavior field value to 'Default
B.
Set the Asset Amendment Behavior field value to 'Allow Refund'.
C.
Set the Asset Conversion field value to 'One per Quote'.
D.
Conversion field value to 'None'.