What should a user do to pause a segment activation with the intent of using that segment again?

A.
Deactivate the segment.
Answers
A.
Deactivate the segment.
B.
Delete the segment.
Answers
B.
Delete the segment.
C.
Skip the activation.
Answers
C.
Skip the activation.
D.
Stop the publish schedule.
Answers
D.
Stop the publish schedule.
Suggested answer: A

Explanation:

The correct answer is A. Deactivate the segment. If a segment is no longer needed, it can be deactivated through Data Cloud and applies to all chosen targets.A deactivated segment no longer publishes, but it can be reactivated at any time1. This option allows the user to pause a segment activation with the intent of using that segment again.

The other options are incorrect for the following reasons:

B . Delete the segment.This option permanently removes the segment from Data Cloud and cannot be undone2. This option does not allow the user to use the segment again.

C . Skip the activation.This option skips the current activation cycle for the segment, but does not affect the future activation cycles3. This option does not pause the segment activation indefinitely.

D . Stop the publish schedule.This option stops the segment from publishing to the chosen targets, but does not deactivate the segment4. This option does not pause the segment activation completely.

1:Deactivated Segmentarticle on Salesforce Help

2:Delete a Segmentarticle on Salesforce Help

3:Skip an Activationarticle on Salesforce Help

4:Stop a Publish Schedulearticle on Salesforce Help

asked 23/09/2024
Shawn Sullivan
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first