The product owner determines how many product backlog items the developers select for the sprint in the sprint planning.

A.
False, the scrum master does that
Answers
A.
False, the scrum master does that
B.
True
Answers
B.
True
C.
True, in line with what was promised to the stakeholders
Answers
C.
True, in line with what was promised to the stakeholders
D.
True, if the developers have enough capacity
Answers
D.
True, if the developers have enough capacity
E.
False, the project manager does that
Answers
E.
False, the project manager does that
F.
False
Answers
F.
False
Suggested answer: F

Explanation:

It is false, the developers select the items, because they will have to commit to it.