Several scrum teams share the scrum master. Developers of multiple teams approach the scrum master, because they need fulltime commitment from the same technical specialist for the next sprint. What should the scrum master consider for the response to this problem? Choose the two best answers.

A.
The need for a stable velocity
Answers
A.
The need for a stable velocity
B.
The benefit of the teams figuring it out theirselves
Answers
B.
The benefit of the teams figuring it out theirselves
C.
The need to have all developers busy with work
Answers
C.
The need to have all developers busy with work
D.
The ability of the scrum teams to produce integrated increments
Answers
D.
The ability of the scrum teams to produce integrated increments
Suggested answer: B, D

Explanation:

The working increment is the goal of the sprint and should be kept in mind. The self-managing aspect of the teams is also crucial to take in mind. Stable velocity and optimally used developers are not the scrum master's concern.