List of questions
Related questions
Question 93 - PSD discussion
Which of the following two best describe a ready product backlog item?
A.
It is a complete user story with all the necessary components
B.
It is well understood by the developers and product owner at the sprint planning
C.
It has been changed from unready to ready status in the tracking tool
D.
It has been fully described in the user requirements analysis
E.
It can most likely be done within one sprint
Your answer: