Question 94 - PSD discussion
The CEO demands a feature from the developers during the sprint. What should the developers do?
A.
Add the item to the next sprint
B.
Add the item to the current sprint and work harder
C.
Add the item to the current sprint and leave out something that is less important
D.
Inform the product owner, so the PO can deal with the CEO
Your answer: