Who creates documentation included with a working increment?

A.
Scrum requires no documentation
Answers
A.
Scrum requires no documentation
B.
Technical writers
Answers
B.
Technical writers
C.
Scrum master
Answers
C.
Scrum master
D.
Product owner
Answers
D.
Product owner
E.
Developers
Answers
E.
Developers
Suggested answer: E

Explanation:

It is part of the increment, so it is part of the work of the developers.