Question 103 - PSD discussion
When is it most appropriate for developers to change the Definition of Done
A.
During the sprint planning when they can't fit enough into the sprint
B.
Prior to starting a new sprint
C.
In the retrospective when it turns out they can improve quality
D.
Prior to starting a new project