When is it most appropriate for developers to change the Definition of Done

A.
During the sprint planning when they can't fit enough into the sprint
Answers
A.
During the sprint planning when they can't fit enough into the sprint
B.
Prior to starting a new sprint
Answers
B.
Prior to starting a new sprint
C.
In the retrospective when it turns out they can improve quality
Answers
C.
In the retrospective when it turns out they can improve quality
D.
Prior to starting a new project
Answers
D.
Prior to starting a new project
Suggested answer: C

Explanation:

The definition of done can be changed when more is learnt. This always needs to be done aiming at a high quality usable increment. The best time to reflect on this is the retrospective.