Question 12 - SPS discussion
During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on
Team Red completing PBI 1.
All else being equal, which PBI is most concerning?
(choose the best answer)
A.
PBI 2, because it has the most dependencies.
B.
PBI 1, because it is on the top of the Product Backlog.
C.
PBI 1, because it is the first piece of work with a dependency.
D.
PBI 2, because there is a dependency with a different team on work that occurs within the same Sprint.