Question 13 - SPS discussion
Scenario A: Nexus Sprint Review with Five Scrum Teams
There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room.
Since teams are not using a shared environment, what is likely?
(choose the best two answers)
A.
The Sprint is too short.
B.
The Nexus has not yet reached the integration phase.
C.
There is no single Integrated Increment.
D.
The Nexus Integration Team is lacking or nonexistent.