Using the Request type field on a resource plan, which options can be used to request a resource?

Choose 3 answers

A.
Day
Answers
A.
Day
B.
FTE
Answers
B.
FTE
C.
Person Days
Answers
C.
Person Days
D.
Hours
Answers
D.
Hours
E.
Month
Answers
E.
Month
Suggested answer: B, C, D

Explanation:

Using the Request type field on a resource plan, you can request a resource by specifying the amount of FTE, person days, or hours that you need for a task or a project. FTE stands for full-time equivalent and represents the percentage of a standard work week that a resource can perform. Person days are the number of days that a resource works on a task or a project. Hours are the number of hours that a resource works on a task or a project. You can find more information about the Request type field in theProduct Documentationfor ServiceNow.

asked 23/09/2024
Eric Jones
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first