What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

A.
Accrual
Answers
A.
Accrual
B.
Commitment
Answers
B.
Commitment
C.
Baseline
Answers
C.
Baseline
D.
Forecast
Answers
D.
Forecast
Suggested answer: C

Explanation:

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.