Question 238 - AZ-400 discussion
Your company implements an Agile development methodology.
You plan to implement retrospectives at the end of each sprint.
Which three questions should you include? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A.
Who performed well?
B.
Who should have performed better?
C.
What could have gone better?
D.
What went well?
E.
What should we try next?