You manage a project by using Azure Boards. You manage the project code by using GitHub.

You have three work items that have IDs of 456. 457. and 458.

You need to create a pull request that will be linked to all the work items. The solution must set the state of work item 456 to done.

What should you add to the commit message?

A.
Done #456, #457, #A53
Answers
A.
Done #456, #457, #A53
B.
Fixes #456, #457, #458
Answers
B.
Fixes #456, #457, #458
C.
Fixes #AB456, #AB457, #AB4S8
Answers
C.
Fixes #AB456, #AB457, #AB4S8
D.
#AB456, #AB457, #AB458 Completed #AB456
Answers
D.
#AB456, #AB457, #AB458 Completed #AB456
Suggested answer: C