A change advisory board authorized a setting change so a technician is permitted to Implement the change. The technician successfully implemented the change. Which of the following should be done next?

A.
Document the date and time of change
Answers
A.
Document the date and time of change
B.
Document the purpose of the change
Answers
B.
Document the purpose of the change
C.
Document the risk level
Answers
C.
Document the risk level
D.
Document the findings of the sandbox test
Answers
D.
Document the findings of the sandbox test
Suggested answer: A

Explanation:

The correct answer is

A. Document the date and time of change. After implementing a change, the technician should document the date and time of change in the change log or record. This helps to track the change history, monitor the change performance, and identify any issues or incidents related to the change.

Documenting the date and time of change is also a good practice for auditing and compliance purposes.

Documenting the purpose of the change (B) and the risk level © are steps that should be done before implementing the change, not after. These are important information that help to justify, prioritize, and plan the change. The purpose of the change should explain why the change is needed and what benefits it will bring to the organization. The risk level should assess the potential impact and probability of the change causing any problems or disruptions to the business.

Documenting the findings of the sandbox test (D) is also a step that should be done before implementing the change, not after. A sandbox test is a way of testing the change in an isolated environment that mimics the production environment. This helps to verify that the change works as expected and does not cause any errors or conflicts with other systems or processes. The findings of the sandbox test should be documented and reviewed by the change advisory board (CAB) before approving the change for implementation.

Reference:

What is a Change Advisory Board? (Overview, Roles, and Responsibilities)

Best Practices in Change Management

10 Top change management best practices

asked 02/10/2024
Valerio Pietrantoni
44 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first