A change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed. Which of the following should be updated before requesting approval again?

A.
Scope of change
Answers
A.
Scope of change
B.
Risk level
Answers
B.
Risk level
C.
Rollback plan
Answers
C.
Rollback plan
D.
End user acceptance
Answers
D.
End user acceptance
Suggested answer: C

Explanation:

The rollback plan should be updated before requesting approval again. A rollback plan is a plan for undoing a change if it causes problems, and it is an important part of any change management process. If the change advisory board did not approve the requested change due to the lack of alternative actions if implementation failed, then updating the rollback plan would be the best way to address this concern.