Salesforce Certified Hyperautomation Specialist Practice Test 2
Question 1 / 20
The current date and time is September 28, 2022, at 9:00 a.m.
A process running in a single Secured Session is scheduled to start September 28, 2022, at 10:00 a.m., and run every 45 minutes.
If the process takes one hour to complete when it runs for the first time, when will it run for the second time?