ISC CAP Practice Test - Questions Answers, Page 11
List of questions
Related questions
Question 101
Courtney is the project manager for her organization. She is working with the project team to complete the qualitative risk analysis for her project. During the analysis Courtney encourages the project team to begin the grouping of identified risks by common causes. What is the primary advantage to group risks by common causes during qualitative risk analysis?
Question 102
You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your company, on several risks within the project. Nancy understands that through qualitative analysis you have identified 80 risks that have a low probability and low impact as the project is currently planned. Nancy's concern, however, is that the impact and probability of these risk events may change as conditions within the project may change. She would like to know where will you document and record these 80 risks that have low probability and low impact for future reference. What should you tell Nancy?
Question 103
You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project. They would like you to analyze the project risks with a goal of improving the project's performance as a whole. What approach can you use to achieve the goal of improving the project's performance through risk analysis with your project stakeholders?
Question 104
Your project is an agricultural-based project that deals with plant irrigation systems. You have discovered a byproduct in your project that your organization could use to make a profityou're your organization seizes this opportunity it would be an example of what risk response?
Question 105
You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?
Question 106
Which of the following NIST documents provides a guideline for identifying an information system as a National Security System?
Question 107
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Question 108
There are seven risks responses that a project manager can choose from. Which risk response is appropriate for both positive and negative risk events?
Question 109
What course of action can be taken by a party if the current negotiations fail and an agreement cannot be reached?
Question 110
Which of the following is the acronym of RTM?
Question