ISC CAP Practice Test - Questions Answers, Page 12

List of questions
Question 111

Thomas is the project manager of the NHJ Project for his company. He has identified several positive risk events within his project and he thinks these events can save the project time and money. Positive risk events, such as these within the NHJ Project are also known as what?
Question 112

You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?
Question 113

Which of the following are the tasks performed by the owner in the information classification schemes? Each correct answer represents a part of the solution.
Choose three.
Question 114

Which of the following approaches can be used to build a security program? Each correct answer represents a complete solution. Choose all that apply.
Question 115

Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?
Question 116

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?
Question 117

Which of the following phases of the DITSCAP C&A process is used to define the C&A level of effort, to identify the main C&A roles and responsibilities, and to create an agreement on the method for implementing the security requirements?
Question 118

A security policy is an overall general statement produced by senior management that dictates what role security plays within the organization. Which of the following are required to be addressed in a well designed policy?
Each correct answer represents a part of the solution. Choose all that apply.
Question 119

The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.
Question 120

Which of the following objectives are defined by integrity in the C.I.A triad of information security systems? Each correct answer represents a part of the solution.
Choose three.
Question