ISC CAP Practice Test - Questions Answers, Page 19
List of questions
Related questions
Which of the following acts is used to recognize the importance of information security to the economic and national security interests of the United States?
What approach can a project manager use to improve the project's performance during qualitative risk analysis?
Which of the following is used in the practice of Information Assurance (IA) to define assurance requirements?
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?
Which of the following access control models uses a predefined set of access privileges for an object of a system?
Which of the following describes residual risk as the risk remaining after risk mitigation has occurred?
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?
Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?
Which of the following classification levels defines the information that, if disclosed to the unauthorized parties, could be reasonably expected to cause exceptionally grave damage to the national security?
Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?
Question