ISC CAP Practice Test - Questions Answers, Page 20
List of questions
Related questions
Which of the following individuals is responsible for monitoring the information system environment for factors that can negatively impact the security of the system and its accreditation?
Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?
Which of the following is a temporary approval to operate based on an assessment of the implementation status of the assigned IA Controls?
SIMULATION
Fill in the blank with an appropriate word.
________ ensures that the information is not disclosed to unauthorized persons or processes.
Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?
Which of the following is a standard that sets basic requirements for assessing the effectiveness of computer security controls built into a computer system?
The Phase 4 of DITSCAP C&A is known as Post Accreditation. This phase starts after the system has been accredited in Phase 3. What are the process activities of this phase?
Each correct answer represents a complete solution. Choose all that apply.
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?
Rob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed - even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?
Question