ISC CAP Practice Test - Questions Answers, Page 24
List of questions
Related questions
Which of the following are the objectives of the security certification documentation task? Each correct answer represents a complete solution. Choose all that apply.
Which of the following statements about System Access Control List (SACL) is true?
Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?
You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan. Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?
What NIACAP certification levels are recommended by the certifier?
Each correct answer represents a complete solution. Choose all that apply.
You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?
Information Security management is a process of defining the security controls in order to protect information assets. What are the security management responsibilities?
Each correct answer represents a complete solution. Choose all that apply.
Which of the following are included in Technical Controls?
Each correct answer represents a complete solution. Choose all that apply.
You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
Question