ISC CAP Practice Test - Questions Answers, Page 26
List of questions
Related questions
Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology.
Initial testing of the technology makes the use of it look promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?
Which of the following is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold?
BS 7799 is an internationally recognized ISM standard that provides high level, conceptual recommendations on enterprise security. BS 7799 is basically divided into three parts. Which of the following statements are true about BS 7799? Each correct answer represents a complete solution. Choose all that apply.
Gary is the project manager for his organization. He is working with the project stakeholders on the project requirements and how risks may affect their project.
One of the stakeholders is confused about what constitutes risks in the project. Which of the following is the most accurate definition of a project risk?
You work as a project manager for TechSoft Inc. You are working with the project stakeholders onthe qualitative risk analysis process in your project.
You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?
You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?
Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to last 14 months and has a budget at completion of $4,555,000.
Tracy's organization will receive a bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that there are several opportunities within the project to save on time by crashing the project work. Crashing the project is what type of risk response?
Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?
You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis.
You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?
Question