Which of these tools or techniques should be used to sequence work to deliver value quickly?
A.
Minimum business Increment (MBI)
B.
Minimum viable product (MVP)
C.
Panning Poker
D.
Work in process (WIP) limits
What is the main role of the team lead?
A.
Ensure that the team builds the product right.
B.
Build the product.
C.
Ensure that the team builds the right product.
D.
Coordinate the building of the product.
Which is not a feature of a user story?
A.
Achievable
B.
Negotiable
C.
Estimable
D.
Testable
How does a value stream map help the learn to minimize waste?
A.
By helping the team to identify problem areas in the path for realizing value
B.
By helping the lean to focus on the construction phase
C.
By helping the lean to reduce delays in the workflow process
D.
By helping the team to apply the five Whys root cause method to all parts of the stream
What is the role of the product owner?
A.
Coordinate the product.
B.
Inspect the product.
C.
Build the right product.
D.
Organize the product team.
In Team Estimation
A.
You first estimate the relative sizes of al stories, then assign numbers to them.
B.
Each team is ranked in order of importance for completing a task.
C.
Members of a group define what criteria will be used for determining the 'Definition of Done. *
D.
You estimate what roles will be necessary in order to complete user stories.
Which characteristic describes a good user story according to the f.N.V.E.S.T. mnemonic?
A.
Incremental
B.
Satisfactory
C.
Tangible
D.
Valuable
Which of the following statements accurately describes a complex adaptive system?
A.
A system algorithm used to predict how people are going to work together or what the results of that work will be
B.
The process used in agile teams to evolve their ways of working and motivate change in those they interact with outside of the team
C.
The process by which a collection of interacting teams and groups adapt their way of working to the organizational context and project requirements
D.
A system in which a perfect understanding of the individual parts does not automatically convey a perfect understanding of the whole system's behavior
A scrum master needs to set up a team for a long-term project that has the potential for significant budgeting and tracking overhead.
What type of team should the scrum master set up?
A.
A long-standing team
B.
A protect team
C.
A cross-functional team
D.
A shared services team
What are the three phases of DAD's delivery life cycle?
A.
Commencement. Creation. Evolution
B.
Initiation. Foundation. Conversion
C.
Introduction. Substance, Alteration
D.
Inception. Construction. Transition