Which of the following is NOT one of the benefits of reducing work-in-progress?

Allows you to multi-task between many high priority items
Allows you to multi-task between many high priority items
Reduces the lead time
Reduces the lead time
Creates a greater incentive to prioritize
Creates a greater incentive to prioritize
Create focus
Create focus
Comment (0)
Suggested answer: A