VMware 2V0-13.24 Practice Test - Questions Answers, Page 2

List of questions
Question 11

During a transformation project kick-off meeting, an architect highlights specific areas on which to focus while developing the new conceptual design. Which statement is the business requirement?
The solution must continue to operate even in case of an entire datacenter failure.
The project should use the existing storage devices within the data center.
Sites must support a network latency of less than 12 ms RTT.
There is no budget specifically assigned for disaster recovery.
Business requirements in VCF reflect organizational goals or operational needs, distinct from technical constraints or assumptions. Option A, 'The solution must continue to operate even in case of an entire datacenter failure,' is a business requirement as it states a high-level objective---continuous operation---driving the need for disaster recovery (DR) and high availability (HA), directly impacting business continuity. Option B (using existing storage) is a constraint, limiting design choices. Option C (latency) is a technical requirement, specifying performance metrics. Option D (no DR budget) is a financial constraint, not a requirement. VCF's conceptual design phase prioritizes identifying such business drivers to shape the solution, and A aligns with this focus on resilience.
Question 12

The following requirements were identified in an architecture workshop for a virtual infrastructure design project.
REQ001: All virtual machines must satisfy the Recovery Point Objective (RPO) of fifteen (15) minutes or less in a disaster recovery (DR) situation
REQ002: Service level availability must satisfy 99.999% measured yearly.
Which two test cases will validate these requirements?
Simulate or invoke an outage of the primary datacenter. All virtual machines must be restored within fifteen (15) minutes or less.
Simulate or invoke an outage of the primary datacenter. All virtual machines must not lose more than one (1) hour of data prior to the outage.
Simulate or invoke an outage of the primary datacenter. All virtual machines must not lose more than fifteen (15) minutes of data prior to the outage.
Simulate or invoke an outage of the primary datacenter. All virtual machines must be restored within one (1) hour or less.
REQ001 specifies an RPO of 15 minutes or less, meaning the maximum data loss in a DR scenario is 15 minutes. REQ002 demands 99.999% availability, but test cases focus on DR validation, so RPO is primary here. Option C directly tests RPO: if VMs lose no more than 15 minutes of data, the requirement is met, aligning with vSphere Replication or vSAN stretched clusters in VCF 5.2, which can achieve such RPOs. Option A tests restoration within 15 minutes, which, while related to Recovery Time Objective (RTO), also implies minimal data loss if achieved, indirectly validating RPO in a failover context. Option B (1 hour of data loss) exceeds the 15-minute RPO, failing REQ001. Option D (1-hour restoration) tests RTO, not RPO, and isn't tied to data loss limits. VCF DR solutions emphasize these metrics, making A and C the precise validations.
Question 13

As part of a new VMware Cloud Foundation (VCF) deployment, a customer is planning to implement vSphere IaaS control plane. What component could be installed and enabled to implement the solution?
Aria Automation
NSX Edge networking
Storage DRS
Aria Operations
The vSphere IaaS (Infrastructure-as-a-Service) control plane in VCF 5.2 enables self-service provisioning and automation of virtualized resources, integrating with vSphere's Supervisor Cluster for cloud-like functionality. Option A, 'Aria Automation' (formerly vRealize Automation), is the correct component, providing orchestration, cloud templates, and self-service portals to manage IaaS workloads in VCF. It integrates with vSphere and NSX to deliver this capability. Option B, 'NSX Edge networking,' focuses on networking, not IaaS control. Option C, 'Storage DRS,' optimizes storage but isn't a control plane. Option D, 'Aria Operations,' is for monitoring, not provisioning. VMware's documentation confirms Aria Automation's role in VCF IaaS.
Question 14

An architect is preparing a VI Workload Domain design with a dedicated NSX instance. The workload domain is planned to grow up to 300 ESXi hosts within the next six months. Which is the minimum NSX Manager form factor that should be recommended by the architect for this VI Workload Domain to support the forecasted growth?
Large
Medium
Extra Small
Small
NSX Manager in VCF 5.2 comes in form factors (Small, Medium, Large) with capacity limits based on managed objects (hosts, VMs, etc.). A VI Workload Domain with a dedicated NSX instance growing to 300 ESXi hosts requires a form factor supporting this scale. Per NSX-T 3.2 sizing guidelines (used in VCF 5.2), the Large form factor supports up to 1,024 hosts, 12,000 VMs, and extensive networking objects, making it suitable for 300 hosts and future growth. Medium supports up to 256 hosts, which is close but risks being exceeded with additional VMs or objects. Small (64 hosts) and Extra Small (lab use) are insufficient. The architect must recommend 'Large' (A) to ensure scalability and performance for this VI domain.
Question 15

A customer is deploying VCF at a new datacenter location. They will migrate their workloads from the existing datacenter to the new VCF platform over six months. Both datacenters will run simultaneously for six months during the migration. Which of the following should be a documented risk?
Six months may not be enough time to complete the migration.
There will be connectivity between the two locations.
Bandwidth between the two locations is sufficient to accommodate the workload migration.
Workloads will be powered off during migration.
In VCF design, risks are potential issues that could jeopardize project success, documented to prompt mitigation planning. Option A, 'Six months may not be enough time to complete the migration,' is a valid risk because workload migration complexity (e.g., application dependencies, data volume, testing) could exceed the timeline, a common challenge in VCF deployments. Option B (connectivity) is a fact, not a risk, unless qualified as unreliable. Option C (sufficient bandwidth) is an assumption or requirement, not a risk unless proven inadequate. Option D (powering off workloads) is a design choice, not an inherent risk without evidence. VCF migration planning emphasizes timeline risks, making A the best choice.
Question 16

An architect had gathered the following requirements and constraints for a VMware Cloud Foundation (VCF) deployment.
Requirements:
* User interface (UI) SSL certificates must have a maximum validity of 6 months.
* Have the least possible administrative time to install and renew certificates.
* Each certificate must be created on a per VCF component basis.
Constraints:
* Limited administrative skillsets on SSL certificate administration
* Limited operational expenditure budget for SSL certificates
Which design decision should be made to satisfy the stated requirement(s) and constraint(s)?
Use wildcard certificates
Use and configure integration with a certificate vendor such as DigiCert
Disable the use of SSL certificates for user interfaces
Use and configure integration with Microsoft Certificate Authority (CA)
The requirements demand per-component certificates with 6-month validity and minimal admin effort, while constraints limit skills and budget. Option D, 'Use and configure integration with Microsoft Certificate Authority (CA),' meets all criteria: Microsoft CA (integrated via SDDC Manager in VCF 5.2) supports individual certificates per component (e.g., vCenter, NSX), allows short validity periods, automates renewal (reducing effort), and leverages existing infrastructure (low cost, skill-friendly). Option A (wildcard certificates) violates per-component needs. Option B (DigiCert) incurs higher costs and requires more skill. Option C (disabling SSL) compromises security, failing compliance. Microsoft CA aligns with VCF's certificate management capabilities.
Question 17

A design requirement has been specified for a new VMware Cloud Foundation (VCF) instance. All managed workload resources must be lifecycle managed with the following criteria:
* Development resources must be automatically reclaimed after two weeks
* Production resources will be reviewed yearly for reclamation
* Resources identified for reclamation must allow time for review and possible extension
What capability will satisfy the requirements?
Aria Suite Lifecycle Content Management
Aria Operations Rightsizing Recommendations
Aria Automation Lease Policy
Aria Automation Project Membership
Lifecycle management of resources in VCF 5.2 involves automation tools like Aria Automation. Option C, 'Aria Automation Lease Policy,' allows setting expiration dates for resources (e.g., 2 weeks for dev, 1 year for prod), automatically reclaiming them unless extended during a review period, directly meeting all criteria. Option A (Aria Suite Lifecycle) manages software deployment, not resource lifecycles. Option B (Aria Operations Rightsizing) provides sizing insights, not reclamation automation. Option D (Project Membership) controls access, not lifecycles. Aria Automation's lease policies are designed for this exact purpose in VCF, integrating with cloud zones and projects.
Question 18

A VMware Cloud Foundation design incorporates the following technical requirements:
All management components must have their login sessions timeout after 2 minutes of inactivity.
Communication between management components should be limited to required ports only.
Modifications required by compliancy should not impact the management components' functionality.
What would be the recommendation from a design perspective that would aid in achieving the above requirements?
Question 19

An architect is designing a new VMware Cloud Foundation (VCF)-based Private Cloud solution. During the requirements gathering workshop, a network team stakeholder stated that:
* The solution must ensure that any physical networking component has N + N redundancy.
* The solution must ensure that inter-datacenter network links are diversely routed.
When documenting the design, how should the architect classify these requirements?
Question 20

Which Operating System (OS) is not supported by Aria Operations for OS and Application Monitoring?
Question