SAP C_TS452_2410 Practice Test - Questions Answers

List of questions
Question 1

Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier?
Note: There are 2 correct answers to this question.
Set a maximum lot size in the quota arrangement item and select the 1x checkbox
Assign a rounding profile in the material master record of the planned material
Assign the indicator for quota splitting to the lot-sizing procedure being used
Set a maximum quola quantity in the quota arrangement item for each supplier
Question 2

Which of the following SAP Fiori apps must you use to set up the following Situation Handling use case: Quantity Deficit in Supplier's Delivery? Note: There are 2 correct answers to this question.
Manage Situation Types
Manage Teams and Responsibilities
Manage Situation Objects
Monitor Situations
Question 3

Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.
Whether a goods receipt needs to be confirmed
Whether reminders for outstanding confirmations are required
Whether a confirmation type is relevant for MRP
Whether a confirmation type is a prerequisite for a goods receipt
Question 4

How can you completely block a material for procurement in a plant? Note: There are 2 correct answers to this question.
Create a blocking entry in the supplier master record
Create a quota arrangement entry with a quantity of zero
Use a relevant plant-specific material status in the material master
Create an entry in the source list with a blocking indicator and NO supplier
Question 5

Where can you enter a rounding profile?
Note: There are 2 correct answers to this question.
Lot-sizing procedure
Purchasing info record
Source list
Material master
Question 6

What is the definition of an opening horizon?
The time available for the MRP run to convert a requirement into a schedule line or a planned order
The time available for the MRP run to convert requirements into purchase requisitions or planned orders
The time available for the MRP controller to convert a purchase requisition into a purchase order or a schedule line
The time available for the MRP controller to convert a planned order into a purchase requisition or a production order
Question 7

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.
Planned order
Purchase order
Delivery schedule line
Purchase requisition
Question 8

Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
Flag materials that have been subject to an activity relevant to MRP
Carry out a lot-size calculation for every material with net requirements
Carry out a net requirement calculation for every material included in the planning run
Perform backward scheduling to determine the availability dates of purchase requisitions
Question 9

What does SAP S/4HANA use to determine the sequence in which materials are planned?
Source list
MRP group
Low-level code
Quota arrangement
Question 10

Which of the following does the material type control? Note: There are 3 correct answers to this question.
Procurement type of a material
Batch requirement for a material
Material number assignment
Field selection in the material master
Material availability check