ExamGecko
Home / ISTQB / CTAL-TM / List of questions
Ask Question

ISTQB CTAL-TM Practice Test - Questions Answers

List of questions

Question 1

Report Export Collapse

Which of the following is a typical use of risk analysis?

Identifying the appropriate depth of testing for each identified risk

Identifying the appropriate depth of testing for each identified risk

Deciding what personnel should be assigned to which tests

Deciding what personnel should be assigned to which tests

Determining the design of the tests used to mitigate each identified risk

Determining the design of the tests used to mitigate each identified risk

Forecasting the product delivery date

Forecasting the product delivery date

Suggested answer: A
Explanation:

Risk analysis is typically used to identify the appropriate depth of testing for each identified risk. This involves assessing the potential impact and likelihood of risks to prioritize testing efforts and ensure that high-risk areas are thoroughly tested.

Reference: The ISTQB Advanced Level Test Manager syllabus and e-learning materials emphasize the importance of organizing and leading risk identification and risk analysis sessions.The outcomes of these sessions are used for test estimation, planning, monitoring, and control, which includes determining the depth of testing based on the identified risks

asked 18/02/2025
Rajeev R Kumar
44 questions

Question 2

Report Export Collapse

Your company is installing a third-party enterprise-wide business software package. This is the first time the company has done anything like this.

Which technique would be the best one to use to estimate the testing effort? [3]

Estimated developer effort and lines of code

Estimated developer effort and lines of code

Industry averages

Industry averages

Review of the installation guide

Review of the installation guide

Past experience with in-house projects

Past experience with in-house projects

Suggested answer: B
asked 18/02/2025
Chrysovalantis Oikonomopoulos
40 questions

Question 3

Report Export Collapse

You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk mitigation list, never mind any from the medium or low-risk lists.

What is the most effective action you should take? [3]

Use a random selection algorithm to pick tests from the high, medium, and low risk mitigation lists - thereby ensuring that each risk list has some mitigation.

Use a random selection algorithm to pick tests from the high, medium, and low risk mitigation lists - thereby ensuring that each risk list has some mitigation.

Present your risk mitigation progress and project status to the project's stakeholders, and request additional time or assistance in re-prioritizing the remaining high-risk items.

Present your risk mitigation progress and project status to the project's stakeholders, and request additional time or assistance in re-prioritizing the remaining high-risk items.

Concentrate testing in areas that have already found numerous problems.

Concentrate testing in areas that have already found numerous problems.

Retest the highest risk areas to ensure no regressions have occurred.

Retest the highest risk areas to ensure no regressions have occurred.

Suggested answer: B
Explanation:

When faced with the inability to complete all items on the high-risk mitigation list within the remaining time, the most effective action is to communicate the current progress and challenges to the stakeholders. This allows for a collaborative decision-making process to re-prioritize the remaining high-risk items and potentially secure additional resources or time to address them.

Reference: The ISTQB Advanced Level Test Manager syllabus emphasizes the importance of continuous monitoring and control of test activities to achieve project objectives, which includes assessing and reporting relevant and timely test status to project stakeholders123.It also highlights the need for test managers to organize and lead risk identification and analysis sessions, and use the results for test planning, monitoring, and control2.

asked 18/02/2025
Martin White
41 questions

Question 4

Report Export Collapse

You are the Test Manager for a critical system and are using a risk-based approach for this project.

Which of the following would most clearly convey the current status to project stakeholders? [3]

A scatter chart showing test execution status

A scatter chart showing test execution status

A Pareto graph showing requirements coverage

A Pareto graph showing requirements coverage

A pie chart showing residual risk

A pie chart showing residual risk

A bar graph showing defect density

A bar graph showing defect density

Suggested answer: C
Explanation:

The most clear way to convey the current status to project stakeholders is to use a pie chart showing residual risk. This is because a risk-based approach focuses on identifying, analyzing, and prioritizing the risks that may affect the quality of the system, and allocating testing resources accordingly. A pie chart can visually represent the proportion of each risk category (such as high, medium, or low) in the overall risk profile, and show how much risk has been reduced or remains after testing. This can help the stakeholders to understand the current level of confidence in the system, and the potential impact of any remaining risks.Reference:Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association,ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration,Managing the Test Team - ISTQB not-for-profit association

asked 18/02/2025
Venkata Nandyala
43 questions

Question 5

Report Export Collapse

You are the Test Manager of a risk-based testing effort. You develop the following graph to show residual risk. Assume that 'Risks mitigated' represents passed tests and 'Risks not mitigated' represents failed tests and other discovered failures.

Which of the following answers best represents what the graph shows? [3]

ISTQB CTAL-TM image Question 5 63875516202583642817449

Project is behind schedule based on bug fix rate

Project is behind schedule based on bug fix rate

Project is on schedule based on total number of test cases executed

Project is on schedule based on total number of test cases executed

Project is at risk due to the number of failed tests

Project is at risk due to the number of failed tests

Project is ahead of schedule due to number of risks addressed

Project is ahead of schedule due to number of risks addressed

Suggested answer: C
Explanation:

The graph indicates that a significant portion of risks, 29%, have not been mitigated, which suggests that these are either failed tests or other discovered failures. This level of unmitigated risk puts the project at risk, as it implies that there are still substantial issues that need to be addressed.

Reference: The ISTQB Advanced Level Test Manager documents outline the importance of risk-based testing and the interpretation of residual risk graphs.These graphs are used to communicate the current status of risk mitigation efforts in the project, and a high percentage of unmitigated risks is a clear indicator of potential problems1.

asked 18/02/2025
yusuf sivrikaya
46 questions

Question 6

Report Export Collapse

Which of the following is a key characteristic of a management review?

Used to assess project risks

Used to assess project risks

Used to check consistency of and deviation from the system requirements

Used to check consistency of and deviation from the system requirements

Run by a moderator

Run by a moderator

Conducted by an external group to assess process compliance

Conducted by an external group to assess process compliance

Suggested answer: D
Explanation:

A management review, particularly in the context of software testing and quality assurance, often involves an external group or higher-level management team that reviews the processes and procedures to ensure compliance with specified standards or objectives. This can include assessing the effectiveness of current practices, identifying areas for improvement, and ensuring that the project aligns with organizational or industry standards. This type of review is distinct from other forms of reviews like technical reviews or walkthroughs, which might focus more on the technical aspects or consistency of system requirements.

asked 18/02/2025
Patrick Neason
41 questions

Question 7

Report Export Collapse

Which of the following is likely to occur if reviewers do not have an adequate level of technical knowledge?

There will be no impact as long as they have sufficient business knowledge.

There will be no impact as long as they have sufficient business knowledge.

There will be no impact as long as they have sufficient process knowledge.

There will be no impact as long as they have sufficient process knowledge.

The review is likely to be less efficient.

The review is likely to be less efficient.

The review will be shorter because any technical aspect can be skipped.

The review will be shorter because any technical aspect can be skipped.

Suggested answer: C
Explanation:

If reviewers do not have an adequate level of technical knowledge, they may not be able to identify and describe anomalies in the product or project under review1.They may also not be able to provide constructive feedback or suggestions for improvement2.This can result in a less efficient review, as the review objectives may not be met, the review process may take longer, or the review outcome may be of lower quality3. Therefore, option C is the correct answer.Option A is incorrect because having sufficient business knowledge is not enough to perform a technical review, as business knowledge does not cover the technical aspects of the product or project4.Option B is incorrect because having sufficient process knowledge is not enough to perform a technical review, as process knowledge does not cover the technical aspects of the product or project4.Option D is incorrect because skipping any technical aspect can compromise the quality and completeness of the review, and may lead to defects or risks in the product or project5.Reference:1: ISTQB Glossary, Reviewer2: ISTQB Advanced Level Test Manager Syllabus, Section 2.2.23: ISTQB Advanced Level Test Manager Syllabus, Section 2.2.34: ISTQB Advanced Level Test Manager Syllabus, Section 2.3.15: ISTQB Advanced Level Test Manager Syllabus, Section 2.3.2

asked 18/02/2025
Neha Dua
47 questions

Question 8

Report Export Collapse

Which of the following metrics would be most beneficial to collect to determine the effectiveness of a review process? [2]

The number of defects found in production for each module that was reviewed

The number of defects found in production for each module that was reviewed

The development language used to create each module that was reviewed

The development language used to create each module that was reviewed

The elapsed time between each module's review and its corresponding deployment into production

The elapsed time between each module's review and its corresponding deployment into production

The business criticality of each module that was reviewed

The business criticality of each module that was reviewed

Suggested answer: A
Explanation:

The effectiveness of a review process can be measured by how well it detects and removes defects from the work products being reviewed1.One of the metrics that can indicate the defect detection capability of a review process is the number of defects found in production for each module that was reviewed2. This metric can show how many defects escaped the review process and were not detected until the software was deployed. A lower number of defects found in production means a higher review effectiveness. Therefore, option A is the correct answer. Option B is incorrect because the development language used to create each module that was reviewed is not relevant to the review process effectiveness. Option C is incorrect because the elapsed time between each module's review and its corresponding deployment into production is not a measure of defect detection or removal, but rather a measure of development speed or efficiency.Option D is incorrect because the business criticality of each module that was reviewed is not a measure of defect detection or removal, but rather a measure of risk or priority.Reference:1: ISTQB Advanced Level Test Manager Syllabus, Section 2.3.22:Software Testing Metrics: What is, Types & Example

asked 18/02/2025
Raphael Oliveir
49 questions

Question 9

Report Export Collapse

What is the purpose of tracking efficiency metrics for a formal review?

These metrics can be used to determine who participated in the review.

These metrics can be used to determine who participated in the review.

These metrics can be used to determine if the review was a good use of resources.

These metrics can be used to determine if the review was a good use of resources.

These metrics can be used to determine the quality of the reviewed object.

These metrics can be used to determine the quality of the reviewed object.

These metrics can be used to determine the speed with which defects were fixed.

These metrics can be used to determine the speed with which defects were fixed.

Suggested answer: B
Explanation:

Efficiency metrics for a formal review are used to measure the cost-effectiveness of the review process, such as the time spent on the review, the number of defects found, and the return on investment1. These metrics can help to evaluate if the review was a good use of resources, such as human effort, money, and tools. Therefore, option B is the correct answer. Option A is incorrect because efficiency metrics do not track who participated in the review, but rather how they performed. Option C is incorrect because efficiency metrics do not measure the quality of the reviewed object, but rather the quality of the review process.Option D is incorrect because efficiency metrics do not measure the speed with which defects were fixed, but rather the speed with which defects were detected.Reference:1:How to manage formal reviews & management audits? Skills, metrics ...

asked 18/02/2025
Alexandru Ouatu
51 questions

Question 10

Report Export Collapse

You are a Test Manager on a new project. The software that is being created will be used to control the projectors in movie theaters. This is a time critical project because the software must be released before the Christmas holiday season which has the highest movie attendance of the year.

You have decided to implement a review process for the work products that are a part of this release to save both time and money. In order to expedite the training, you brought in a consultant to train the participants and moderators in proper review processes. Your team is enthusiastic about participating in the reviews.

Your manager is questioning the money you have spent on this training effort. He wants to know how you intend to justify the expense when you present your numbers at the annual budget meeting in February.

What would be a reasonable way for you to justify the cost of the training and the reviews when you present your information at the budget meeting? [3]

Compare the production defects from the previous project to the production defects from this project and explain the cost benefits due to the defect reduction in production.

Compare the production defects from the previous project to the production defects from this project and explain the cost benefits due to the defect reduction in production.

Show the defects that were found in the review sessions and show the cost of quality regarding the perfect phase containment for those caught defects.

Show the defects that were found in the review sessions and show the cost of quality regarding the perfect phase containment for those caught defects.

Explain that the reviews are a way of expanding the knowledge of your people and will motivate them to work harder and faster, thus saving money for the company.

Explain that the reviews are a way of expanding the knowledge of your people and will motivate them to work harder and faster, thus saving money for the company.

Calculate the ROI using the difference between the cost of the reviews and the cost of dealing with defect escapes.

Calculate the ROI using the difference between the cost of the reviews and the cost of dealing with defect escapes.

Suggested answer: D
Explanation:

The cost of the training and the reviews can be justified by showing the return on investment (ROI) that they generate.ROI is a measure of the profitability of an investment, calculated by dividing the net benefit by the cost1. The net benefit of the training and the reviews is the difference between the cost of the reviews and the cost of dealing with defect escapes. Defect escapes are defects that are not detected during the review process and are found later in the development or testing phases, or even in production.The cost of dealing with defect escapes includes the cost of rework, testing, debugging, deployment, customer support, and potential loss of reputation or revenue2.The cost of the reviews includes the cost of the training, the time spent by the reviewers and moderators, the tools and resources used, and the overheads3. By calculating the ROI, you can demonstrate how much money the training and the reviews have saved or earned for the company, compared to the alternative of not conducting them. Therefore, option D is the correct answer. Option A is incorrect because comparing the production defects from the previous project to the production defects from this project does not account for the cost of the reviews or the cost of dealing with defect escapes in other phases. Option B is incorrect because showing the defects that were found in the review sessions and the cost of quality regarding the perfect phase containment for those caught defects does not account for the cost of the training or the cost of dealing with defect escapes in production.Option C is incorrect because explaining that the reviews are a way of expanding the knowledge of your people and motivating them to work harder and faster is not a quantifiable or verifiable way of justifying the cost of the training and the reviews.Reference:1: ISTQB Glossary, Return on Investment2: ISTQB Advanced Level Test Manager Syllabus, Section 2.3.23:How to manage formal reviews & management audits? Skills, metrics ...

asked 18/02/2025
Francesco Balducci
40 questions
Total 128 questions
Go to page: of 13
Search

Related questions