Which of the following is one of the MOST important outcomes of any Practice/Microprocess Planning?
Metrics that will be used to measure progress or value
The prioritized list of items for the next Sprint
A detailed plan on how to achieve the Practice/Microprocess goal
A and B
Effective planning for a practice or microprocess involves setting measurable outcomes and prioritizing tasks to ensure value delivery.
A . Correct. Metrics are vital to track progress and evaluate the impact of improvements.
B . Correct. Prioritizing the next steps helps the team focus on delivering value incrementally.
C . Incorrect. Agile discourages creating overly detailed plans, favoring adaptability.
D . Correct. Both metrics and prioritization are critical outcomes of effective planning.
ITIL 4: Metrics and priorities in process improvement.
Scrum Guide 2020: Planning and prioritization principles.