Which one of the following is a disadvantage of Water Cooled System?

A.

All components are located inside the CRAC

A.

All components are located inside the CRAC

Answers
B.

Condenser water piping loops long distances

B.

Condenser water piping loops long distances

Answers
C.

Usage of the building's condenser water is less expensive than chilled water

C.

Usage of the building's condenser water is less expensive than chilled water

Answers
D.

Introduces an additional source of liquid

D.

Introduces an additional source of liquid

Answers
Suggested answer: D

Explanation:

Water cooled systems introduce an additional source of liquid, which can be a potential source of contamination and damage to the IT equipment. Additionally, water cooled systems require more maintenance than air cooled systems and are more expensive to install due to the additional cost of the cooling tower, piping, and pumps.

Which mounted system is used to cool small IT environments?

A.

Air Mounted System

A.

Air Mounted System

Answers
B.

Chilled Mounted System

B.

Chilled Mounted System

Answers
C.

Ceiling Mounted System

C.

Ceiling Mounted System

Answers
D.

Floor Mounted System

D.

Floor Mounted System

Answers
Suggested answer: A

Explanation:

An air mounted system is often used to cool small IT environments. This type of cooling system is typically mounted on the wall or ceiling and works by blowing cool air into the room to lower the temperature. Air mounted systems are compact, easy to install and maintain, and can be a cost- effective solution for small spaces.

Which mounted system can use any of the five heat removal methodologies?

A.

Air Mounted System

A.

Air Mounted System

Answers
B.

Chilled Mounted System

B.

Chilled Mounted System

Answers
C.

Ceiling Mounted System

C.

Ceiling Mounted System

Answers
D.

Floor Mounted System

D.

Floor Mounted System

Answers
Suggested answer: C

Data Center Precision Cooling Systems maintain temperature within _____________ degree(s) of their design set point.

A.

1

A.

1

Answers
B.

2

B.

2

Answers
C.

3

C.

3

Answers
D.

5

D.

5

Answers
Suggested answer: A

Whenever electrical power is being consumed in an IT room or data center. __________ is generated.

A.

Heat

A.

Heat

Answers
B.

Static electricity

B.

Static electricity

Answers
C.

Condensation

C.

Condensation

Answers
D.

Humidity

D.

Humidity

Answers
Suggested answer: A

Explanation:

Whenever electrical power is being consumed in an IT room or data center, heat is generated. This heat must be removed in order to maintain an optimal temperature for the equipment, and this is usually done through cooling systems such as air conditioning, air economization, liquid cooling, evaporative cooling, and immersion cooling.

A __________ generator system is a combination of an electrical generator and a mechanical engine mounted together to form a single piece of equipment.

A.

passive

A.

passive

Answers
B.

standby

B.

standby

Answers
C.

active

C.

active

Answers
D.

software

D.

software

Answers
Suggested answer: B

Explanation:

A Standby Generator System is a combination of an electrical generator and a mechanical engine mounted together to form a single piece of equipment. The generator provides power to essential appliances and equipment in the event of a power outage. Standby Generator Systems are usually powered by gasoline, diesel, natural gas, or propane, and they are designed to be able to be activated quickly in the event of an emergency.

True or False: Fuel availability generally dictates the type of standby generator selected

A.

True

A.

True

Answers
B.

False

B.

False

Answers
Suggested answer: A

Explanation:

Fuel availability generally dictates the type of standby generator selected as different types of generators use different types of fuel. For example, gasoline generators are typically used in residential or small commercial applications, while diesel generators are usually used in larger industrial and commercial applications. Propane or natural gas generators may also be used, depending on the availability of fuel sources.

Which component is designed to protect electrical equipment from damage caused by overload or short circuit?

A.

Transfer Switch

A.

Transfer Switch

Answers
B.

Stabiliser

B.

Stabiliser

Answers
C.

Transient

C.

Transient

Answers
D.

Circuit Breaker

D.

Circuit Breaker

Answers
Suggested answer: D

Explanation:

A circuit breaker is a device designed to protect electrical equipment from damage caused by overload or short circuit. Circuit breakers are designed to detect when too much current is flowing through a circuit and to shut the circuit off when that happens. This protects the equipment from damage due to overloading or short circuiting, and it also helps prevent fires and other accidents.

True or False: A grounded wire is connected to metal appliance cases

A.

True

A.

True

Answers
B.

False

B.

False

Answers
Suggested answer: A

Explanation:

A grounded wire is connected to metal appliance cases in order to provide a safe path for electricity to flow in the event of a short circuit or other electrical problem. This helps to protect the appliance and the people using it from potential electrical shocks, and it also helps prevent fires and other accidents.

What is a Data Center?

A.

A building or portion of a building whose primary function is to research new data.

A.

A building or portion of a building whose primary function is to research new data.

Answers
B.

A room in a building dedicated to monitoring data and information.

B.

A room in a building dedicated to monitoring data and information.

Answers
C.

A building or a portion of a building whose primary function is to house a computer room and its related support areas

C.

A building or a portion of a building whose primary function is to house a computer room and its related support areas

Answers
D.

A building or a portion of a building where debugging takes place

D.

A building or a portion of a building where debugging takes place

Answers
Suggested answer: C

Explanation:

A building or a portion of a building whose primary function is to house a computer room and its related support areas. A Data Center is a secure, temperature-controlled environment that houses computer systems, equipment, and associated components. It is typically used to store, process, and distribute large amounts of data and information. Data Centers typically include server racks, storage arrays, network switches, firewalls, and other components necessary for the operation of computer systems.