Question 31

Report
Export
Collapse

A Lean Principle that addresses efficiency by the process worker is called ____________________?

Visual Factory
Visual Factory
Supervising
Supervising
Training
Training
Standardizing
Standardizing
Suggested answer: D
asked 23/09/2024
Hairul Isman Abdul Gaffar
38 questions

Question 32

Report
Export
Collapse

While management of a company must set the stage for all improvement efforts, which of these 5S's is primarily driven by management?

Straighten
Straighten
Sort
Sort
Shine
Shine
Sustain
Sustain
Suggested answer: D
asked 23/09/2024
Richard Fuller
28 questions

Question 33

Report
Export
Collapse

As part of a Visual Factory plan __________ cards are created and utilized to identify areas in need of cleaning and organization.

Kanban
Kanban
Kaizen
Kaizen
Poke-Yoke
Poke-Yoke
WhoSai
WhoSai
Suggested answer: A
asked 23/09/2024
Jean Ducasse
40 questions

Question 34

Report
Export
Collapse

The use of Kanbans work best with pull systems for determining the timing of which products or services are produced.

True
True
False
False
Suggested answer: A
asked 23/09/2024
Michael Madamba
34 questions

Question 35

Report
Export
Collapse

When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make certain the activity is _______________ .

Well documented
Well documented
Removed from the line
Removed from the line
Mistake proofed
Mistake proofed
Highly visible
Highly visible
Suggested answer: C
asked 23/09/2024
Praveen Achankunju
44 questions

Question 36

Report
Export
Collapse

The Lean Principle action in the 5S approach that deals with having those items needed regularly at hand and those items need less regularly stored out of the way is known as ___________.

Shining
Shining
Standardizing
Standardizing
Sustaining
Sustaining
Sorting
Sorting
Suggested answer: D
asked 23/09/2024
Synathia Imafidon
41 questions

Question 37

Report
Export
Collapse

SPC on the outputs is more preferred than SPC on the inputs when implementing SPC for your process.

True
True
False
False
Suggested answer: B
asked 23/09/2024
Kaniamuthan K
41 questions

Question 38

Report
Export
Collapse

Significant variation in process performance is a consequence of several causes that can be classified using which of the terminologies shown. (Note: There are 2 correct answers).

Common
Common
Random
Random
Uneducated
Uneducated
Special
Special
Vital
Vital
Suggested answer: A, D
asked 23/09/2024
MARTIN WEAVER
35 questions

Question 39

Report
Export
Collapse

When it comes to Control one of the most effective means of eliminating defects is to _________________ .

Train personnel often and thoroughly
Train personnel often and thoroughly
Keep a Six Sigma project going on the process at all times
Keep a Six Sigma project going on the process at all times
Design defect prevention into the product
Design defect prevention into the product
Have each process consist of no more than five steps
Have each process consist of no more than five steps
Suggested answer: C
asked 23/09/2024
Ayo dickson
50 questions

Question 40

Report
Export
Collapse

A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.

True
True
False
False
Suggested answer: A