ExamGecko
Home / IIA / IIA-CIA-Part2 / List of questions
Ask Question

IIA IIA-CIA-Part2 Practice Test - Questions Answers, Page 21

List of questions

Question 201

Report Export Collapse

While planning for an accounts payable audit an internal auditor performs an entity level controls analysis. Which of the following statements is true regarding me approach used by the auditor?

It enables the auditor to identify the inherent risks to the effective operation of accounts payable process controls.
It enables the auditor to identify the inherent risks to the effective operation of accounts payable process controls.
It enables the auditor to understand the framework of the activities and associated accounts payable subprocesses
It enables the auditor to understand the framework of the activities and associated accounts payable subprocesses
it enables the auditor to understand the accounts payable process and its flow, including key steps and systems.
it enables the auditor to understand the accounts payable process and its flow, including key steps and systems.
It enables the auditor to categorize the population of transactions within the accounts payable process
It enables the auditor to categorize the population of transactions within the accounts payable process
Suggested answer: B
Explanation:

Performing an entity-level controls analysis helps the auditor understand the overarching framework of activities and subprocesses within the accounts payable function. This approach provides a high-level view of the control environment and how different processes interrelate and contribute to the overall control objectives. By understanding the framework, the auditor can identify key controls, assess their design and implementation, and determine areas of potential risk. This foundational understanding is crucial before delving into more detailed, transaction-level testing.

Reference:

Institute of Internal Auditors (IIA), International Standards for the Professional Practice of Internal Auditing (Standards), Standard 2130 -- Control.

asked 18/09/2024
Thomas Schmitt
49 questions

Question 202

Report Export Collapse

The chief audit executive was asked to define me internal audit activity s key performance indicators (KPIs) tor the upcoming year. The KPIs must measure efficiency and effectiveness. Which of the following is an example of a KPI that measures effectiveness?

Internal audit reports are consistently submitted prior to the audit report deadline
Internal audit reports are consistently submitted prior to the audit report deadline
Post engagement surveys completed by management indicate a 'meets or exceeds expectations' idling
Post engagement surveys completed by management indicate a 'meets or exceeds expectations' idling
There is a significant reduction of travel costs per project over the next fiscal year
There is a significant reduction of travel costs per project over the next fiscal year
Internal auditors identify a minimum number of issues and provide recommendations to address them for each audit
Internal auditors identify a minimum number of issues and provide recommendations to address them for each audit
Suggested answer: B
Explanation:

A key performance indicator (KPI) that measures effectiveness reflects how well the internal audit activity achieves its objectives and meets stakeholder expectations. Post-engagement surveys completed by management, indicating a 'meets or exceeds expectations' rating, directly measure the perceived value and impact of the audit work. This KPI shows whether the internal audit function is providing useful insights, recommendations, and assurance that align with management's needs and expectations, thus demonstrating the effectiveness of the audit activity.

Reference:

Institute of Internal Auditors (IIA), Practice Guide -- Measuring Internal Audit Effectiveness and Efficiency.

asked 18/09/2024
Bates, Michael
42 questions

Question 203

Report Export Collapse

An internal auditor was assigned to review controls in the accounts payable function. Most of tie accounts payable processes are performed by a third-party service provider. The auditor included in the audit report a number of control deficiencies involving processes performed by the service provider. The service provider requested a copy of the report Which of Vie following would be the most appropriate response from the chief audit executive (CAE)?

The CAE would automatically sand a copy of the report to the service provider as many of the findings relate to Via area managed by the service provider
The CAE would automatically sand a copy of the report to the service provider as many of the findings relate to Via area managed by the service provider
The CAE may distribute the report to tie service provider at no cost, after consulting with legal counsel and tie chief compliance officer
The CAE may distribute the report to tie service provider at no cost, after consulting with legal counsel and tie chief compliance officer
The CAE may provide a copy of the audit report to the service provider If an agreement & signed and the service provider agrees to reimburse the cost of the audit D, The CAE should benchmark with other organization in the industry by consorting with colleagues and distribute the report only I it is an acceptable practice m the industry
The CAE may provide a copy of the audit report to the service provider If an agreement & signed and the service provider agrees to reimburse the cost of the audit D, The CAE should benchmark with other organization in the industry by consorting with colleagues and distribute the report only I it is an acceptable practice m the industry
Suggested answer: B
Explanation:

According to internal auditing standards and best practices, the distribution of audit reports, especially those involving third-party service providers, must be handled with caution. The CAE should consult with legal counsel and the chief compliance officer before distributing the audit report to ensure that the organization's legal and compliance obligations are met. This ensures that any sensitive information is protected and that the distribution is aligned with the organization's policies and contractual agreements with the service provider.

The Institute of Internal Auditors (IIA) Standards

Internal Audit Guidelines on Confidentiality and Distribution of Audit Reports

asked 18/09/2024
jaimie lloyd
48 questions

Question 204

Report Export Collapse

As a result of server managements assumption of risk there is residual risk that exceeds me organisation's risk appetite. Which of the following actions would be most appropriate for the chief audit executive to take?

ignore the responsibility of addressing the residual risk
ignore the responsibility of addressing the residual risk
Assume the responsibility of addressing the residual risk
Assume the responsibility of addressing the residual risk
Ensure senior management acknowledges residual risk
Ensure senior management acknowledges residual risk
Communicate with the board the issue of residual risk
Communicate with the board the issue of residual risk
Suggested answer: D
Explanation:

The CAE has a responsibility to communicate significant risks to the board, particularly when the residual risk exceeds the organization's risk appetite. By communicating with the board, the CAE ensures that the highest level of governance is aware of the risk and can make informed decisions about how to address it. Ignoring the risk, assuming responsibility without authority, or only ensuring senior management's acknowledgment without further action would be insufficient and not in line with the CAE's duties.

The Institute of Internal Auditors (IIA) Standards

Internal Audit's Role in Risk Management

asked 18/09/2024
ivaylo Skechleiev
39 questions

Question 205

Report Export Collapse

An internal auditor at a bank informed the branch manager of a malfunctioning lock on one of the vaults. The risk associated with this issue was deemed significant by the chief audit executive (CAE), and immediate remediation was recommended However during a follow-up engagement the branch manager told the CAE that the risk was actually not significant, hence no action was taken. What is the most appropriate next step for the CAE?

Inform senior management that the branch manager deeded to cancel the committed action plan without any previous communication
Inform senior management that the branch manager deeded to cancel the committed action plan without any previous communication
Discuss the issue with the board which has ultimate responsibility to resolve the risk
Discuss the issue with the board which has ultimate responsibility to resolve the risk
Have another discussion with the branch manager attempt to change his view, and encourage him to movement the recommendations
Have another discussion with the branch manager attempt to change his view, and encourage him to movement the recommendations
Document the branch manager's decision to accept the risk otherwise, no other speak: course of action is required.
Document the branch manager's decision to accept the risk otherwise, no other speak: course of action is required.
Suggested answer: B
Explanation:

If the branch manager decides not to act on a significant risk that was previously acknowledged, the CAE should escalate the issue to the board. The board has ultimate responsibility for risk management and needs to be informed about significant risks and the decisions made by management regarding these risks. This ensures transparency and allows the board to take appropriate action if necessary.

The Institute of Internal Auditors (IIA) Standards

Risk Management Frameworks and Reporting

asked 18/09/2024
Quintin van Rooyen
50 questions

Question 206

Report Export Collapse

In which of the following ways can the internal audit activity new engagement opportunities?

By defining activities by business processes.
By defining activities by business processes.
By looking external factors such as product complaints.
By looking external factors such as product complaints.
By looking at activities by businesses cost centers.
By looking at activities by businesses cost centers.
By defining activities by the organization chart.
By defining activities by the organization chart.
Suggested answer: A
Explanation:

Defining activities by business processes is a structured approach that allows the internal audit activity to identify engagement opportunities effectively. This method ensures that all critical processes are reviewed systematically and that risks are identified and assessed in the context of how they affect the entire business process. This approach is comprehensive and aligns with best practices in internal auditing.

The Institute of Internal Auditors (IIA) Standards

Internal Audit Planning and Engagement Standards

asked 18/09/2024
Juli Santo
40 questions

Question 207

Report Export Collapse

For an action plan to be effective, it should be designed primarily to address which of the following elements of an observation?

Condition
Condition
Root cause
Root cause
Criteria
Criteria
Recommendation
Recommendation
Suggested answer: B
Explanation:

For an action plan to be effective, it must address the root cause of an observation. The root cause is the underlying reason why a problem or issue has occurred. By targeting the root cause, the action plan can help prevent the recurrence of the issue and ensure long-term resolution. Addressing only the condition or the symptoms of the problem may lead to temporary fixes, whereas understanding and resolving the root cause leads to more sustainable improvements.

Reference:

Institute of Internal Auditors (IIA), Practice Guide -- Root Cause Analysis.

asked 18/09/2024
ANDREA SIMONELLI
42 questions

Question 208

Report Export Collapse

Which of the following statements is true regarding internal controls?

For assurance engagements internal auditors should plan to assess the effectiveness of all entity-level controls
For assurance engagements internal auditors should plan to assess the effectiveness of all entity-level controls
Poorly designed or deficient entity-level controls can prevent well-designed process controls from working as intended.
Poorly designed or deficient entity-level controls can prevent well-designed process controls from working as intended.
During engagement planning, internal auditors should not discuss the identified key risks and controls with management of the area under review to prevent tipping off probable audit lasts
During engagement planning, internal auditors should not discuss the identified key risks and controls with management of the area under review to prevent tipping off probable audit lasts
Reviewing process maps and flowcharts is an appropriate method for the internal a auditor to identify all key risks and controls during engagement planning
Reviewing process maps and flowcharts is an appropriate method for the internal a auditor to identify all key risks and controls during engagement planning
Suggested answer: B
Explanation:

Entity-level controls set the tone and establish the framework for the overall control environment within an organization. If these controls are poorly designed or deficient, they can undermine the effectiveness of process-level controls, even if those controls are well-designed. Entity-level controls include governance, risk management, and compliance controls that influence the entire organization. Therefore, deficiencies at this level can have a widespread impact, preventing lower-level controls from functioning properly.

Reference:

Institute of Internal Auditors (IIA), International Standards for the Professional Practice of Internal Auditing (Standards), Standard 2130 -- Control.

asked 18/09/2024
Cornel Sasu
41 questions

Question 209

Report Export Collapse

An engagement work program o of greatest value to audit management when which of the following is true?

The work program provides more detailed support for the audit report
The work program provides more detailed support for the audit report
The work program helps determined the required amount of audit resources
The work program helps determined the required amount of audit resources
The work program helps ensure tie achievement of the engagement objectives
The work program helps ensure tie achievement of the engagement objectives
The work program assists the auditor n developing and managing audit tests
The work program assists the auditor n developing and managing audit tests
Suggested answer: C
Explanation:

An engagement work program is of greatest value to audit management when it helps ensure the achievement of the engagement objectives. The work program outlines the audit procedures and tests that need to be performed to gather sufficient and appropriate evidence to support the audit findings and conclusions. By aligning the work program with the engagement objectives, auditors can focus their efforts on the most critical areas, ensure that all necessary steps are taken, and ultimately achieve the intended outcomes of the audit.

Reference:

Institute of Internal Auditors (IIA), International Standards for the Professional Practice of Internal Auditing (Standards), Standard 2240 -- Engagement Work Program.

asked 18/09/2024
Maxime SELLY
45 questions

Question 210

Report Export Collapse

According to IIA guidance, which of re following actions should the internal auditor take immediately after having considered fraud scenarios and identified and prioritized fraud risks?

Determine which controls if any are in place to mitigate the fraud risks
Determine which controls if any are in place to mitigate the fraud risks
Follow protocol for internal reporting and investigating fraud allegations
Follow protocol for internal reporting and investigating fraud allegations
Research frauds that nave occurred t\ similar organizations
Research frauds that nave occurred t\ similar organizations
Incorporate the fraud risk assessment into the engagement plan
Incorporate the fraud risk assessment into the engagement plan
Suggested answer: A
Explanation:

After considering fraud scenarios and identifying and prioritizing fraud risks, the next immediate action for the internal auditor is to determine which controls are in place to mitigate those risks. This step involves assessing the effectiveness of existing controls and identifying any gaps where controls may be insufficient or absent. Understanding the control environment is crucial for developing a comprehensive fraud risk assessment and ensuring that appropriate measures are in place to prevent and detect fraud.

Reference:

Institute of Internal Auditors (IIA), Practice Guide -- Internal Auditing and Fraud.

asked 18/09/2024
Ahmed Khan
48 questions
Total 492 questions
Go to page: of 50
Search

Related questions