Microsoft MB-330 Practice Test - Questions Answers, Page 26

List of questions
Question 251

A company is considering using Planning Optimization instead of the built-in master planning engine.
What are three benefits of Planning Optimization? Each correct answer presents a complete solution.
Question 252

A company uses Planning Optimization.
You need to ensure that the purchase price trade agreement lead time is used for an item.
What should you do?
Question 253

A company performs internal inspections of a specific product before releasing the products. This task adds two days for product handling once the product is in the warehouse. This process leads to delays in shipping. You need to resolve the issues. What should you change?
Question 254

A company enables purchase trade agreements for Planning Optimization.
You need to be able to evaluate purchase trade agreements.
Which three configurations must be set up? Each correct answer presents part of the solution.
Select all answers that apply.
Question 255

A buyer reviews the orders generated by Planning Optimization. The buyer observes that the output for some orders appears incorrect.
The buyer reviews the history and planning logs.
Which two types of information are in the history and planning logs? Each correct answer presents part of the solution.
Select all answers that apply.
Question 256

A company is evaluating sales pricing strategies in a costing version of a bill of materials (BOM) product that will use a cost-plus-markup strategy.
You need to configure the system to provide three prices based on different profit models.
Where should you configure the markup values?
Select only one answer.
Question 257

A company requires that a percentage of the building overhead costs as well as a percentage of overall labor must be added to a costing sheet for each item.
The company also requires that the labor and overhead costs be calculated independently and then rolled up to a total amount.
Which three actions should you perform to meet the requirements?
Select all answers that apply.
Question 258

A manufacturing company uses standard costs for raw materials.
The company opens a new manufacturing location that will have different standard costs for the raw materials. The differences in costs must be reflected on the finished goods.
You need to configure the site setup for the different costs.
Which two configurations can be set up?
Select all answers that apply.
Question 259

You run Planning Optimization. You create a static master plan with a plan filter for A and B items.
Purchasing agents for the A items start to review the A item output. You must re-run planning for the B items due to a change. Re-running the B items must not impact the existing planned orders for the A items.
You need to re-run planning for the B items.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
Select all answers that apply.
Question 260

A buying agent is evaluating vendors for sourcing an item. Prices and lead times vary by vendor.
The buyer requires that the planning engine be set up to provide the best price while considering the lead time.
Manual correction must not be required after planned purchase orders have been created.
Which two actions should you perform to meet the requirements? Each correct answer presents part of the solution.
Select all answers that apply.
Question