Which phase of the ADM establishes a set of Principles?

A.
Preliminary Phase
A.
Preliminary Phase
Answers
B.
Phase A
B.
Phase A
Answers
C.
Phase D
C.
Phase D
Answers
D.
Phase G
D.
Phase G
Answers
E.
Phase H
E.
Phase H
Answers
Suggested answer: A

In which Phase of the ADM does the business scenario technique figure most prominently?

A.
Preliminary
A.
Preliminary
Answers
B.
Architecture Vision
B.
Architecture Vision
Answers
C.
Business Architecture
C.
Business Architecture
Answers
D.
Information Systems Architectures
D.
Information Systems Architectures
Answers
E.
Technology Architecture
E.
Technology Architecture
Answers
Suggested answer: B

Which one of the following best describes the Architecture Vision document?

A.
An agreement between development partners and the sponsor on architecture deliverables
A.
An agreement between development partners and the sponsor on architecture deliverables
Answers
B.
A description of how the new capability will address stakeholder concerns
B.
A description of how the new capability will address stakeholder concerns
Answers
C.
A description of the scope and approach for completion of the architecture project
C.
A description of the scope and approach for completion of the architecture project
Answers
D.
A set of quantitative statements outlining requirements on the implementation
D.
A set of quantitative statements outlining requirements on the implementation
Answers
E.
A set of rules and guidelines to support fulfilling the mission of the organization
E.
A set of rules and guidelines to support fulfilling the mission of the organization
Answers
Suggested answer: B

Which of the following best describes TOGAF?

A.
An abstract framework for the development of standards and processes for a business architecture
A.
An abstract framework for the development of standards and processes for a business architecture
Answers
B.
A collection of components organized to accomplish a specific set of functions
B.
A collection of components organized to accomplish a specific set of functions
Answers
C.
A process model, best practices and assets to aid production, use and maintenance of enterprise architectures
C.
A process model, best practices and assets to aid production, use and maintenance of enterprise architectures
Answers
D.
A reference model containing taxonomy defining terminology for an enterprise architecture, together with an associated graphic
D.
A reference model containing taxonomy defining terminology for an enterprise architecture, together with an associated graphic
Answers
E.
A system development lifecycle method for software engineering
E.
A system development lifecycle method for software engineering
Answers
Suggested answer: C

Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?

A.
Phase E
A.
Phase E
Answers
B.
Phase F
B.
Phase F
Answers
C.
Phase G
C.
Phase G
Answers
D.
Phase H
D.
Phase H
Answers
E.
Requirements Management
E.
Requirements Management
Answers
Suggested answer: C

Which one of the following statements about the Requirements Management phase is true?

A.
All requirements fed into the phase are prioritized, and those of low priority are deferred until the next iteration of the ADM cycle
A.
All requirements fed into the phase are prioritized, and those of low priority are deferred until the next iteration of the ADM cycle
Answers
B.
The phase generates the requirements for a given ADM cycle using the Business Scenario technique
B.
The phase generates the requirements for a given ADM cycle using the Business Scenario technique
Answers
C.
The phase manages the flow of requirements, storing them, and feeding them in and out of the relevant ADM phases
C.
The phase manages the flow of requirements, storing them, and feeding them in and out of the relevant ADM phases
Answers
D.
The phase operates like a waiting room, and all requirements fed in to the phase must be resolved by the end of the current ADM cycle
D.
The phase operates like a waiting room, and all requirements fed in to the phase must be resolved by the end of the current ADM cycle
Answers
E.
The phase resolves the requirements that are fed into it from the other ADM phases
E.
The phase resolves the requirements that are fed into it from the other ADM phases
Answers
Suggested answer: C

Which of the following are interests important to the stakeholders in a system?

A.
Requirements
A.
Requirements
Answers
B.
Principles
B.
Principles
Answers
C.
Concerns
C.
Concerns
Answers
D.
Architecture viewpoints
D.
Architecture viewpoints
Answers
E.
Architecture views
E.
Architecture views
Answers
Suggested answer: C

An ADM cycle can be used to establish an Architecture Capability within an organization. Which architecture produced in such a cycle would describe the architecture processes and organization structure?

A.
Technology Architecture
A.
Technology Architecture
Answers
B.
Data Architecture
B.
Data Architecture
Answers
C.
Application Architecture
C.
Application Architecture
Answers
D.
Business Architecture
D.
Business Architecture
Answers
Suggested answer: D

Which does TOGAF standard define as the structure of components, their inter-relationships, and the principles guiding their design and evolution over time?

A.
An architecture view
A.
An architecture view
Answers
B.
An artifact
B.
An artifact
Answers
C.
An architecture
C.
An architecture
Answers
D.
A deliverable
D.
A deliverable
Answers
E.
A model
E.
A model
Answers
Suggested answer: C

Which of the following describes the practice by which the enterprise architecture is managed and controlled at an enterprise-wide level?

A.
Architecture governance
A.
Architecture governance
Answers
B.
Corporate governance
B.
Corporate governance
Answers
C.
IT governance
C.
IT governance
Answers
D.
Technology governance
D.
Technology governance
Answers
E.
Portfolio governance
E.
Portfolio governance
Answers
Suggested answer: A
Total 296 questions