Question 61

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

You are serving as the Lead Architect for an enterprise architecture project team within a leading multinational pharmaceutical and medical devices manufacturer. Its brands include numerous household names for medications and first aid supplies.

The company has a long history of innovating new treatments for many common illnesses and diseases. Prior to launching a new treatment, the company has to demonstrate its effectiveness and safety in a set of clinical trials that satisfy the regulatory requirements of the countries in the target markets. All clinical trials are undertaken by its research laboratories, which employ over 10,000 people at separate facilities in the United Kingdom, United States, Sweden, France, Canada, India, China and Japan. In addition to internal research and development activities the company is also involved in publicly funded collaborative research projects, with other industrial and academic partners.

The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.

The Enterprise Architecture group is a mature organization. They use the TOGAF 9 ADM with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant.

The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. She has stated that the changes to the enterprise architecture for the new system will need to be rolled out in stages on a regional basis that minimizes disruptions to ongoing clinical trials.

Refer to the Scenario You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s). Based on TOGAF, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 62

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

Your role is that of Lead Enterprise Architect within the headquarters of a large fast food chain. The chain manages over 6000 restaurants across 24 countries.

Each restaurant in the chain is an independently owned and operated franchise. Many of the restaurants use have been with the franchise since its initial startup phase and still use the first generation IT systems deployed over 15 years ago.

The CEO of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services to help them complete with the increasing competition from coffee shops.

This strategy is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.

These changes will provide the chain with improved products, including healthier alternatives in their menu, and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions.

The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.

In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.

Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the franchise.

Refer to the scenario

You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision.

Based on TOGAF, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 63

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company. The company has over 15,000 outsourcing professionals and works on some of the world's largest outsourcing projects.

Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services. Roughly half of its turnover comes from the private sector and half from the public sector.

With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company has recently had a number of high profile projects that have overrun on budget and under delivered, thereby damaging its reputation.

The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice.

The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues.

The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This will include three distinct transformations.

The CIO has made it clear that prior to the approval of the detailed implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.

Refer to the Scenario

You have been asked to recommend an approach to satisfy these concerns.

Based on TOGAF, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 64

Report Export Collapse

Please read this scenario prior to answering the question

You are serving as the Lead Architect for a chain of convenience stores, which has over 2000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and use the latest cloud-based point-of-sale (POS) technology to manage their sales and inventory. Cloud-based POS systems store all user data, including sales and inventory in a remote server.

The cloud-based systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible. The stores also act as self-service delivery locations for a large online retailer which further increases the number of potential customers entering the stores.

An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better support the existing environment and accommodate future changes of strategy within the company.

The CIO has stated that the following issues also need to be addressed in the restructuring:

- They need to address problems with data quality and inconsistent data in order to support better decision making and analysis.- The architecture should focus on the needs of the business, not technology.

- To remain competitive, new products and promotions must undergo market trials before deployment across the retail chain. Information systems must be able to manage changes and updates without undue delays.

Refer to the Scenario

[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.] You have been asked to identify the most relevant architecture principles for the current situation.

Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]

Become a Premium Member for full access
  Unlock Premium Member

Question 65

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

You have been assigned the role of Lead Enterprise Architect for a firm that is a major OEM parts supplier to the auto industry. Europe has been the primary market for its products, with just 20% of its output being exported to North America. The firm is planning to expand its exports to North America and also to establish sales in South America and the Asia Pacific region. This will enable them to better ride out recessions in key markets such as Europe. It will also enable the firm to exploit the auto industry move to global platforms.

The firm is organized into business units with each addressing different auto industry sectors. Each business unit has acquired other procedures to expand its manufacturing capacity. This has resulted and manufacturing systems.

The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are joint sponsors of the EA program. The EA program is mature, with an Active Architecture

Board and a well-defined architecture process and standard content templates based on the TOGAF Architecture Content Framework. The EA program is well coordinated with Project Management Office, Systems Development, and Operations functions.

The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.

A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed change and how to manage the associated risks.

Refer to the Scenario

You have been asked how to address the concerns of the CIO.

Based on the TOGAF standard, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 66

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

You are serving as the Lead Architect for the Enterprise Architecture team at a multinational company. The company has grown rapidly by acquisition and has inherited numerous supply chain processes and related IT systems. Several supply chain processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant processes and systems. The company will move to a "Just-in-time" supply chain management so as to keep inventory costs low.

The TOGAF standard is followed for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).

At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created.

The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing supply chain management processes or systems.

The architecture development project has completed Phase A and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:

Become a Premium Member for full access
  Unlock Premium Member

Question 67

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

Your role is that of Lead Enterprise Architect working at the headquarters of a fast food chain. The chain manages over 7500 restaurants across 33 countries.

Each restaurant in the chain is an independently owned and operated franchise.

Many of the restaurants still use the first generation IT systems deployed over 10 years ago. The Chief Operating Officer (COO) of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business including providing its franchisees new support services to help them address the increasing competition from coffee shops. This is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.

The changes will help provide the chain with improved products, including healthier alternatives in the menu, and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions.

The chain has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The CIO is the sponsor of the activity.

In planning the change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the COO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.

Based on the recommendations from the initial study, the decision has been taken for the chain to adopt a packaged suite of integrated applications that is tailored to the needs of the franchise. Refer to the scenario

You have been asked by the Chief Architect to propose the best approach for architecture development to realize the COO's vision.

Based on the TOGAF standard, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 68

Report Export Collapse

Scenario

Please read this scenario prior to answering the question

You have been appointed as a consultant to the Chief Enterprise Architect of a multinational corporation. The corporation has over 100,000 employees and is organized into 10 divisions with operations in over 60 countries and products sold in over 125 countries. It has major research sites at 8 locations worldwide.

The operations of the corporation are subject to legal and regulatory requirements for each country where they operate. The production of its products have governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was conducting a trial for a new product.

The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.

The Enterprise Architecture group is a mature organization. They use the TOGAF ADM with extensions required to support the manufacturing practices and laboratory practices of their target markets. Due to the high sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security, regulatory and privacy issues that are relevant.

The Executive Vice President for Clinical Research in the sponsor of the Enterprise Architecture activity. She has stated that the changes to the Enterprise Architecture for the new system will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographic regions.

Refer to the Scenario

You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).

Based on the TOGAF standard, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 69

Report Export Collapse

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.

The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels, in order to do so this will require wind turbines to be installed over the large areas and in areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.

The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This will allow the production of significantly more salable energy. This new design is ready to go into production.

The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

As part of putting the new design into production, a pilot architecture project has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location.

The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and a low blade failure rate.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief Engineer's concern.

Based on the TOGAF Standard Version 9.2,, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member

Question 70

Report Export Collapse

Please read this scenario prior to answering the question

Your role is that of the Lead Enterprise Architect at a multinational automotive corporation. The company is headquartered in Germany, and manufactures cars, trucks and buses. It has manufacturing plants across North America, South America, Europe and Asia. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.

The company has an ongoing initiative to improve the efficiency of all of its production operations, and in particular to reduce its carbon footprint. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in energy usage could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in one central data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities.

The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are based on the TOGAF standard. At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the global CIO. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.

Refer to the Scenario

You have been asked to select the most appropriate recommendation to ensure that the team evaluated different approaches to the problem and clarifies the requirements for the architecture.

Based on the TOGAF standard, which of the following is the best answer?

Become a Premium Member for full access
  Unlock Premium Member
Total 75 questions
Go to page: of 8
Search

Related questions

Scenario: Vittronics Ltd. Please read this scenario prior to answering the question Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets. The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAFA. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.Refer to the Vittronics Ltd Scenario:You are serving as the Lead Architect for the SPICE project team.As required by TOGAF, the SPICE project team res completed a Business Transformation Readiness Assessment in Phase A (Architecture Vision). In that assessment, it was determined that there are risks associated with the adoption of the Immersive Collaborative Environment. Despite a clear expression of the vision and the business need for utilizing SPICE to accelerate the clinical trials, the researchers have been resisting the change because of concerns about safeguarding individually identifiable information about the subjects who were participating in the trials.You have been asked to recommend how this situation be managed in the implementation planning phases.Based on TOGAF 9, which of the following is the best answer?

Please read this scenario prior to answering the question You are serving as the Lead Architect for a chain of convenience stores, which has over 2000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and use the latest cloud-based point-of-sale (POS) technology to manage their sales and inventory. Cloud-based POS systems store all user data, including sales and inventory in a remote server. The cloud-based systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible. The stores also act as self-service delivery locations for a large online retailer which further increases the number of potential customers entering the stores. An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better support the existing environment and accommodate future changes of strategy within the company. The CIO has stated that the following issues also need to be addressed in the restructuring: - They need to address problems with data quality and inconsistent data in order to support better decision making and analysis.- The architecture should focus on the needs of the business, not technology. - To remain competitive, new products and promotions must undergo market trials before deployment across the retail chain. Information systems must be able to manage changes and updates without undue delays. Refer to the Scenario [Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.] You have been asked to identify the most relevant architecture principles for the current situation. Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]

Scenario Please read this scenario prior to answering the question Your role is that of the Lead Architect working for a government agency responsible for immigration, customs, and border control. The agency was formed by consolidating several smaller government agencies. The agency has established an Enterprise Architecture practice based on TOGAF 9. The CIO is the executive sponsor and has appointed an EA steering team to oversee the practice. There has been a considerable increase in security requirements and immigration service requests in recent years, which have expanded the scope and size of the operations of the agency. As a result, the existing Information Technology architecture no longer meets the required service levels. A significant Enterprise Architecture (EA) initiative is in progress with the goal to improve customer responsiveness and satisfaction, and improve the overall operational efficiency of the agency. The current EA staff members were internal appointments based on a request from the EA steering team to supply a number of suitable individuals for the EA effort. Collectively, they possess a broad range of IT and business analysis skills. However, the CIO has expressed concern about the diverse range of experience within the team. There is concern that the EA staff may be lacking in some of the critical skills that are required to properly conduct EA activities. It had been assumed that any EA-related skill gaps would be overcome by on-the-job mentoring from the senior members of the EA staff. Each architect was expected to attend a TOGAF training course and participate in other skill development activities. A recent review of the EA program revealed that many EA staff members, despite attending multi-day training courses, were not proficient in analyzing or creating the models and artifacts required for their assigned architecture projects. Stakeholders have observed errors and inconsistencies in artifacts and deliverables being submitted for review. Refer to the Scenario The CIO has asked you to recommend a professional development plan for the EA staff in order to address the findings raised in the recent review. Based on TOGAF, which of the following is the best answer?

Please read this scenario prior to answering the question Your role is that of Lead Enterprise Architect for a chain of convenience stores. The chain includes over 15,000 retail outlets throughout the Asia-Pacific region. Each store in the chain is an independently owned and operated franchise. The stores operate 24 hours a day and 7 days a week. Many of the stores have been wirh the franchise for more than 10 years and still use the original IT systems deployed at that time. The CEO of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new services to help them complete with other retail outlets and online retailers. This strategy is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year. The changes will help provide the chain with improved products, and more efficient operations. The stores will also act as delivery and return locations for a large online retailer which will further increase the number of potential customers. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions. The chain has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The CIO is the sponsor of the activity. The Chief Architect engaged the services of a leading consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chin, including detailed requirements and recommendations. Based on the recommendations from the initial study, the decision for the chain to adopt a packegd suite of integrated applications that is tailored to the needs of the franchise has been taken. Refer to the scenario You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision. Based on the TOGAF Standard, Version 9.2 which of the following is the best answer?

Please read this scenario prior to answering the question. You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation. It is organized into two major business groupings: Upstream operations which include exploration for crude oil and natural gas and operating the infrastructure necessary to deliver oil and gas to the market Downstream operations which include the manufacturing, distribution and marketing activities for oil products and chemicals. Safety is a priority for the company, with the aim to ensure it causes zero harm to people and the environment. The company has to satisfy the regulatory requirements of each of the countries it operates in. The downstream business generates a third of the company's profits worldwide and includes more than 30,000 petrol stations and various oil refineries. In some countries it also includes oil refining, a retail petrol station network, lubricans manufacture and marketing, industrial fuel and lubricans sales. The practice for the downstream business has been to operate locally, managed by local "operating companies". The Governing Board is concerned about the risk posed by operating in this complex global environment with a large part of the downstrean business represented by local operating companies. As a result, the Chief Executive Officer (CEO) has appoimted a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues to the corporation. The CCO reports directly to the CEO. The CCO has approved the expenditure of resources to establish an Enterprise Architecture program, and has mandated the use of the TOGAF standard as the framework. He has requested to be Refer to the Scenario You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the local operating companies. Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?

Scenario Please read this scenario prior to answering the question You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors. The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to "leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone. As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces. The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners. The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a crossfunctional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects. TOGAF Standard Version 9.2 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management. Refer to the Scenario In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board. Based on TOGAF, which of the following is the best answer?


Scenario: Please read this scenario prior to answering the Question Your role is that of Lead Enterprise Architect within a vacation property management firm that has been growing through acquisition. The firm manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed on each property is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis. The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year. These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields. The firm has a mature enterprise architecture practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations. Based on the recommendations from the initial study, the firm has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry. Refer to the scenario You have been asked by the Chief Architect to justify the best approach for architecture development to realize the CEO's vision. Based on TOGAF 9, which of the following is the best answer?

Scenario Please read this scenario prior to answering the question Your role is that of Lead Enterprise Architect within the headquarters of a large fast food chain. The chain manages over 6000 restaurants across 24 countries. Each restaurant in the chain is an independently owned and operated franchise. Many of the restaurants use have been with the franchise since its initial startup phase and still use the first generation IT systems deployed over 15 years ago. The CEO of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services to help them complete with the increasing competition from coffee shops. This strategy is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year. These changes will provide the chain with improved products, including healthier alternatives in their menu, and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions. The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations. Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the franchise. Refer to the scenario You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision. Based on TOGAF, which of the following is the best answer?

Scenario Please read this scenario prior to answering the question Your role is that of Lead Enterprise Architect within the staff headquarters of a large hotel chain. The chain manages over 500 hotels across North America and Canada, with another 230 hotels internationally in the United Kingdom, Europe, Australia and New Zealand. Unlike other hotel chains, which are often a mix of company-owned and franchised units, each hotel in the chain is an independently owned and operated franchise. Many of the hotels use the same internal IT systems that they used before they joined the franchise. Until recently, the only requirement that has been placed on each hotel is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis. The CEO of the chain has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services including worldwide reservations, global, national and regional marketing as well as consolidated financials, logistics, and yield management. This strategy is part of the long-term commitment to enhance the brand image and drive superior revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year. These changes will provide the chain with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key national and regional markets to improve yields. The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations. Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry. Refer to the scenario You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision. Based on TOGAF, which of the following is the best answer?