ExamGecko
Home / PMI / PMI-RMP / Practice Test 2
Ask Question

PMI PMI-RMP Practice Test 2

Add to Whishlist
00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Check list analysis

Check list analysis

Cause and effect

Cause and effect

Specialized meeting

Specialized meeting

Quantitative analysis

Quantitative analysis

Comment (0)
Suggested answer: D
Explanation:

In this instance, the project manager should use quantitative analysis to simulate the overall risk outcome. Quantitative analysis techniques, such as Monte Carlo simulation or decision tree analysis, can be used to model the combined effect of individual risks on project objectives. By leveraging historical data, the project manager can generate more accurate and reliable risk assessments, which can help inform risk response strategies and improve project decision-making.

Quantitative analysis is a type of risk analysis that numerically analyzes the effect of identified risks on overall project objectives1.It involves using historical data and other information to estimate the probability and impact of risks, and then applying mathematical techniques such as simulation, sensitivity analysis, decision tree analysis, or expected monetary value analysis to quantify the overall risk exposure of the project2. Quantitative analysis can provide more accurate and objective results than qualitative analysis, which relies on subjective judgments and ratings.Quantitative analysis can also help the project manager prioritize risks, determine the optimal risk response strategy, and allocate contingency reserves3. Therefore, the correct answer is D.

asked 14/11/2024
adnan reubin
37 questions