PRINCE2 Agile Practitioner: PRINCE2 Agile Practitioner Project Management
PRINCE2
This study guide should help you understand what to expect on the exam and includes a summary of the topics the exam might cover and links to additional resources. The information and materials in this document should help you focus your studies as you prepare for the exam.
Related questions
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
A . the event is carried out safely and professionally;
B . staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training team manager made a request for an additional full-time customer subject matter expert (CSME) to be allocated to the Staff Training Team for the next timebox, which is in Stage 3. This person is responsible for health and safety training within the LGA.
What BEST explains why this approach complies with the 'keep teams stable' target?
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
The Event Village Team is holding a workshop to decide how to meet the varied and often conflicting requirements for culturally diverse, healthy and quick food because several days have already been spent trying to establish the way forward. The workshop involves only the Event Village Team without the use of an independent facilitator.
Which reason BEST explains why this workshop is a good application of the 'rich communication' focus area?
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
In order to assess the prevailing agile environment, the project manager made use of the Agilometer. A summary of the results from canvassing the views of key stakeholders involved in the Event Village is provided below:
Slider
Which observation is appropriate at this point?
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
As a: Footballer participating in the event
I want to: Have a private cubicle to change in before my football match, without having to wait for more than 5 minutes
So that: I can be ready for the game
Which statement explains whether the 'function' in this user story is appropriate?
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team has created a plan of 9 timeboxes that always end on a Friday. The senior user has decided to visit the Marketing Team every Friday in order to attend their regular reviews.
Which reason BEST explains whether this is a suitable approach for the 'directing a project' process?
It is a good approach because regular reviews will provide rich information to assess project viability.
It is a good approach because the senior user will be able to oversee the performance of the team.
It is a poor approach because the senior user should focus on looking at the information radiator instead.
It is a poor approach because the reviews should be scheduled as needed, when products are developed.
Explanation:
Regular reviews conducted by the senior user allow for continuous assessment of the project's progress, ensuring that the project remains aligned with its objectives and can adapt to any necessary changes. This ongoing engagement is vital for maintaining project viability and stakeholder involvement.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is concerned that if local schools hold their annual fundraiser on the same day as the football tournament, this may cause attendance to be adversely affected.
The team manager has asked the business analyst to investigate this risk further and report back to the team at the next daily stand-up.
Which BEST explains how this approach manages risk?
It is a good approach because the business analyst is responsible for capturing the wider customer view.
It is a good approach because discussions in the daily stand-up are a way to actively manage risk.
It is a poor approach because the team manager should carry out actions related to risks that may impact delivery.
It is a poor approach because this risk is outside the project's control so it is NOT relevant to the Marketing Team.
Explanation:
The daily stand-up is an opportunity for the team to discuss ongoing issues, including risks. By having the business analyst investigate the potential conflict with the local schools' fundraiser and report back, the team can address this risk proactively and make informed decisions on how to mitigate it, thus managing risk effectively.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox.
One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox.
Which BEST explains how this approach manages change?
It is a good approach because changes at the high level for a timebox will NOT affect the baseline.
It is a good approach because changes to the website information should be based on feedback.
It is a poor approach because exploration is a behaviour that requires a creative environment to enable change.
It is a poor approach because some of the website pages should be moved to the next timebox.
Explanation:
By seeking feedback from staff on rough drawings of the website pages, the Marketing Team can make informed decisions about what content is most valuable and should be prioritized for delivery within the current timebox. This responsive approach allows the team to adapt to feedback effectively, ensuring the final product meets stakeholder needs.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional Information, answer the following question:
For which marketing product would a quality method of automated test-driven development be MOST suited?
The newspaper advertisements.
The banners for the Event Village.
The text and links for the website.
The radio interview.
Explanation:
Automated test-driven development (TDD) is particularly well-suited for digital products like website content, where code and links can be continuously tested for functionality and correctness. This approach allows for rapid iterations and ensures that updates do not introduce errors, making it ideal for maintaining the quality of web content.
Which is consistent with the eight guidance points of PRINCE2 Agile?
The project manager role is NOT required when incorporating IT-only frameworks.
The project manager role is NOT defined by Scrum or Kanban.
Working in an agile way removes the need for a project manager.
A project manager is indicative of a 'command and control' culture.
Explanation:
This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
A . the event is carried out safely and professionally;
B . staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training Team have developed the following user story:
'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.'
Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target?
The training must be delivered so that the volunteers understand the health and safety requirements.
The health and safety training must be delivered before the planned football tournament takes place.
The volunteers will take time to understand the training before they can apply it safely.
The health and safety training should be left out if it cannot be delivered before the football tournament.
Explanation:
Timely delivery of the health and safety training is crucial to ensure that all volunteers are adequately prepared before the event. Meeting this deadline is essential for ensuring a safe environment for the public during the football tournament, making it a priority to adhere to the schedule.
Question