ExamGecko
Home Home / PRINCE2 / PRINCE2 Agile Practitioner

PRINCE2 PRINCE2 Agile Practitioner Practice Test - Questions Answers

Question list
Search
Search

List of questions

Search

Related questions

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Staff Training - Additional information The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that: A . the event is carried out safely and professionally; B . staff members are able to give advice on health and fitness. This is covered by four work packages: 1. Training syllabus: * High-level design of the manual. * Content of each module. 2. Course content for safety and professionalism: * Detailed design of two modules: * Health and Safety including basic first aid. * Customer relations to look after people attending the event. * Piloting the modules with a group of volunteers. 3. Course content tor giving advice on health and fitness: * Detailed design of two modules: * Exercise fundamentals including how to warm up and cool down. * Healthy eating including what types of food are good for you. * Piloting the modules with a group of volunteers. 4. Training delivery: * Production of the training manual; * Delivery of the training to the rest of the volunteers. The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile. Using the Project Scenario and Staff Training Additional information, answer the following question: The Staff Training team manager made a request for an additional full-time customer subject matter expert (CSME) to be allocated to the Staff Training Team for the next timebox, which is in Stage 3. This person is responsible for health and safety training within the LGA. What BEST explains why this approach complies with the 'keep teams stable' target?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: The Event Village Team is holding a workshop to decide how to meet the varied and often conflicting requirements for culturally diverse, healthy and quick food because several days have already been spent trying to establish the way forward. The workshop involves only the Event Village Team without the use of an independent facilitator. Which reason BEST explains why this workshop is a good application of the 'rich communication' focus area?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: In order to assess the prevailing agile environment, the project manager made use of the Agilometer. A summary of the results from canvassing the views of key stakeholders involved in the Event Village is provided below: Slider Which observation is appropriate at this point?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: As a: Footballer participating in the event I want to: Have a private cubicle to change in before my football match, without having to wait for more than 5 minutes So that: I can be ready for the game Which statement explains whether the 'function' in this user story is appropriate?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: Using the Project Scenario and Marketing Additional information, answer the following question: The Marketing Team has created a plan of 9 timeboxes that always end on a Friday. The senior user has decided to visit the Marketing Team every Friday in order to attend their regular reviews. Which reason BEST explains whether this is a suitable approach for the 'directing a project' process?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: Using the Project Scenario and Marketing Additional information, answer the following question: The Marketing Team is concerned that if local schools hold their annual fundraiser on the same day as the football tournament, this may cause attendance to be adversely affected. The team manager has asked the business analyst to investigate this risk further and report back to the team at the next daily stand-up. Which BEST explains how this approach manages risk?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: Using the Project Scenario and Marketing Additional information, answer the following question: The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox. One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox. Which BEST explains how this approach manages change?

Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: Using the Project Scenario and Marketing Additional Information, answer the following question: For which marketing product would a quality method of automated test-driven development be MOST suited?


Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Staff Training - Additional information The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that: A . the event is carried out safely and professionally; B . staff members are able to give advice on health and fitness. This is covered by four work packages: 1. Training syllabus: * High-level design of the manual. * Content of each module. 2. Course content for safety and professionalism: * Detailed design of two modules: * Health and Safety including basic first aid. * Customer relations to look after people attending the event. * Piloting the modules with a group of volunteers. 3. Course content tor giving advice on health and fitness: * Detailed design of two modules: * Exercise fundamentals including how to warm up and cool down. * Healthy eating including what types of food are good for you. * Piloting the modules with a group of volunteers. 4. Training delivery: * Production of the training manual; * Delivery of the training to the rest of the volunteers. The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile. Using the Project Scenario and Staff Training Additional information, answer the following question: The Staff Training Team have developed the following user story: 'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target?

Question 1

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information

The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.

The event village will comprise a number of work packages:

1. Event village design

2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities

3. Stalls which will be sold to local businesses to raise funds for the event:

4. A car park for 200 cars.

5. Temporary facilities including changing rooms, toilets and shower facilities.

6. Dismantling of the event village and clean up.

The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.

Using the Project Scenario and Event Village Additional information, answer the following question:

There is limited space in the Event Village to accommodate all of the equipment, e.g. the trampolines, 'kidz-zone', food tent, car park and changing rooms.

It is difficult to assess whether there is sufficient space from the design drawings. One of the team has suggested physically drawing out the actual space occupied by each facility at the site.

Which statement BEST describes whether this approach is a good application of the frequent releases focus area?

A.

It is a good approach because a physical representation will deliver something of use to the project.

A.

It is a good approach because a physical representation will deliver something of use to the project.

Answers
B.

It is a good approach because a design should be an interim stage of the Event Village work package.

B.

It is a good approach because a design should be an interim stage of the Event Village work package.

Answers
C.

It is a poor approach because releases need to be put into operational use to receive any feedback.

C.

It is a poor approach because releases need to be put into operational use to receive any feedback.

Answers
D.

It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product.

D.

It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product.

Answers
Suggested answer: A

Explanation:

Creating a physical representation of the space occupied by each facility allows the team to visualize and assess the spatial arrangement more effectively. This tangible output is beneficial for the project, providing a clear understanding of how the various components fit together within the limited space, which aligns with the principle of delivering usable outcomes frequently.

asked 03/12/2024
AN KANGWOOK
46 questions

Question 2

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The safety and professionalism course content timebox includes three high-level requirements.

During timebox planning, it was identified that it will not be possible to deliver everything relating to all three of these requirements during the timebox.

What is the effect of setting the time tolerance to zero for the timebox?

A.

It is a good approach because a physical representation will deliver something of use to the project.

A.

It is a good approach because a physical representation will deliver something of use to the project.

Answers
B.

It is a good approach because a design should be an interim stage of the Event Village work package.

B.

It is a good approach because a design should be an interim stage of the Event Village work package.

Answers
C.

It is a poor approach because releases need to be put into operational use to receive any feedback.

C.

It is a poor approach because releases need to be put into operational use to receive any feedback.

Answers
D.

It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product.

D.

It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product.

Answers
Suggested answer: A

Explanation:

Setting the time tolerance to zero means that the team cannot exceed the planned duration of the timebox. This necessitates a focus on prioritizing the requirements to ensure that the most critical aspects can be delivered within the allocated time. Decomposing the high-level requirements helps identify which elements are essential and can be achieved in the time available.

asked 03/12/2024
Allen J Tyson
30 questions

Question 3

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The Staff Training Team has developed the following user stories:

* 'As a volunteer, I want to be trained in healthy eating so that I can answer questions from the public on the long term aims of the LGA during the football tournament.' - Should Have

* As the LGA. I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' - Must Have

A suitably qualified trainer has been scheduled to deliver a course covering both requirements. Unfortunately, there is no-one available from the LGA to quality check the course materials for the healthy eating training until three days after the date scheduled for training delivery.

How should the team respond to this situation?

A.

De-scope the healthy eating training and remove it from the current sprint/work package.

A.

De-scope the healthy eating training and remove it from the current sprint/work package.

Answers
B.

Reschedule the delivery of the combined course until after the healthy eating course materials are likely to be available.

B.

Reschedule the delivery of the combined course until after the healthy eating course materials are likely to be available.

Answers
C.

Remove the requirement for the volunteers to answer questions on the long term aims from the project product description.

C.

Remove the requirement for the volunteers to answer questions on the long term aims from the project product description.

Answers
D.

Use the unchecked healthy eating course materials and hold the combined course on the scheduled date.

D.

Use the unchecked healthy eating course materials and hold the combined course on the scheduled date.

Answers
Suggested answer: B

Explanation:

Rescheduling the training delivery ensures that the volunteers receive the necessary and quality-checked materials for healthy eating, which is important for providing accurate information to the public. This approach maintains the integrity of the training while still addressing the mandatory health and safety training requirement. It prevents the risk of delivering potentially inadequate or unchecked content.

asked 03/12/2024
Charles Smith
28 questions

Question 4

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The Stall Training Team has developed the following user story:

'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.'

There is a high probability that a suitable trainer may not be available to deliver this mandatory training before the football tournament.

How should this risk be managed by the Staff Training Team in accordance with the five targets?

A.

Set its risk tolerance to zero and agree with the project board to immediately find a suitable a trainer in order to meet the deadline.

A.

Set its risk tolerance to zero and agree with the project board to immediately find a suitable a trainer in order to meet the deadline.

Answers
B.

Flex the tolerance for this risk to enable the risk to be accepted by the project board at the current level of probability.

B.

Flex the tolerance for this risk to enable the risk to be accepted by the project board at the current level of probability.

Answers
C.

Set a high risk tolerance in relation to this risk and monitor the situation in order to deliver on time and hit the deadline.

C.

Set a high risk tolerance in relation to this risk and monitor the situation in order to deliver on time and hit the deadline.

Answers
D.

Remove the delivery of health and safety training from the product backlog in order to deliver on time and within the budget.

D.

Remove the delivery of health and safety training from the product backlog in order to deliver on time and within the budget.

Answers
Suggested answer: B

Explanation:

Flexing the risk tolerance allows the team to acknowledge the current situation while enabling the project board to understand and accept the risk. This approach facilitates informed decision-making regarding potential actions to mitigate the risk without immediately resorting to drastic measures, such as removing the training from the backlog. It keeps the requirement for health and safety training in focus while managing expectations around its delivery.

asked 03/12/2024
Tanner Blair
31 questions

Question 5

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The Staff Training Team have developed the following user story:

'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.'

Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target?

A.

The training must be delivered so that the volunteers understand the health and safety requirements.

A.

The training must be delivered so that the volunteers understand the health and safety requirements.

Answers
B.

The health and safety training must be delivered before the planned football tournament takes place.

B.

The health and safety training must be delivered before the planned football tournament takes place.

Answers
C.

The volunteers will take time to understand the training before they can apply it safely.

C.

The volunteers will take time to understand the training before they can apply it safely.

Answers
D.

The health and safety training should be left out if it cannot be delivered before the football tournament.

D.

The health and safety training should be left out if it cannot be delivered before the football tournament.

Answers
Suggested answer: B

Explanation:

Timely delivery of the health and safety training is crucial to ensure that all volunteers are adequately prepared before the event. Meeting this deadline is essential for ensuring a safe environment for the public during the football tournament, making it a priority to adhere to the schedule.

asked 03/12/2024
Laurence Peterson
34 questions

Question 6

Report
Export
Collapse

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The project product description for the sports event includes the following acceptance criteria (AC):

* It must be possible for the training materials to be maintained in the future by the LGA training department.

* The training materials must be usable for future events run by the LGA.

Which reason explains why the team manager should protect the level of quality in relation to the acceptance criteria?

A.

The AC should be delivered as a minimum viable product.

A.

The AC should be delivered as a minimum viable product.

Answers
B.

The AC should be made transparent for maintenance by the training department.

B.

The AC should be made transparent for maintenance by the training department.

Answers
C.

The AC should be met so that the cost of ownership of the materials is acceptable.

C.

The AC should be met so that the cost of ownership of the materials is acceptable.

Answers
D.

The AC should be tested using spikes to trial the maintenance procedures.

D.

The AC should be tested using spikes to trial the maintenance procedures.

Answers
Suggested answer: C

Explanation:

Ensuring that the acceptance criteria are met is crucial for maintaining the quality of the training materials. This not only affects the usability for future events but also impacts the long-term cost of ownership, as high-quality materials will require less maintenance and adaptation over time. Protecting quality helps ensure that the investment in the training materials is justified and sustainable for future use.

asked 03/12/2024
samir Heniche
39 questions

Question 7

Report
Export
Collapse

What does PRINCE2 Agile identify as a 'concept'?

A.

Prioritizing what needs to be delivered.

A.

Prioritizing what needs to be delivered.

Answers
B.

Trusting and not blaming others.

B.

Trusting and not blaming others.

Answers
C.

Setting tolerances for each project objective to establish limits of authority.

C.

Setting tolerances for each project objective to establish limits of authority.

Answers
D.

Using daily stand-up meetings and user stories.

D.

Using daily stand-up meetings and user stories.

Answers
Suggested answer: D

Explanation:

This option reflects key practices in Agile methodologies, emphasizing collaboration and iterative progress, which are central to Agile principles.

asked 03/12/2024
Joe Mon
27 questions

Question 8

Report
Export
Collapse

Which describes a characteristic of business as usual (BAU) work?

A.

Lists of routine modifications, received regularly during the life of existing products. )

A.

Lists of routine modifications, received regularly during the life of existing products. )

Answers
B.

A new team selected to address a specific problem or opportunity.

B.

A new team selected to address a specific problem or opportunity.

Answers
C.

A collection of difficult tasks that are managed together.

C.

A collection of difficult tasks that are managed together.

Answers
D.

A delivery which is part of a larger programme of work.

D.

A delivery which is part of a larger programme of work.

Answers
Suggested answer: A

Explanation:

Routine Operations: BAU encompasses the standard activities and processes that are necessary for the daily functioning of an organization. This includes tasks that are performed regularly and consistently to maintain services, products, and overall operations.

Regular Modifications: BAU work often involves minor updates or modifications to existing products or services. These modifications are typically routine in nature, aimed at improving efficiency, fixing issues, or adapting to changes in the environment without major disruption.

Maintenance and Support: BAU includes maintenance tasks such as monitoring systems, providing customer support, and ensuring compliance with regulations. These tasks ensure that existing products and services continue to function effectively.

Predictable and Structured: Unlike projects that may have a defined start and end date, BAU work is ongoing and tends to follow established procedures. This predictability helps organizations manage their resources effectively.

Focus on Stability: The goal of BAU work is to maintain stability within the organization. While it may involve some level of change (like routine modifications), the primary focus is on ensuring that existing operations run smoothly.

asked 03/12/2024
Vishal Vitthal Pawar
41 questions

Question 9

Report
Export
Collapse

Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile?

A.

Encouraging system improvement through visualization and controlling work in progress.

A.

Encouraging system improvement through visualization and controlling work in progress.

Answers
B.

Providing guidance on tailoring any applicable principles, themes and processes.

B.

Providing guidance on tailoring any applicable principles, themes and processes.

Answers
C.

Reducing quality testing in order to deliver within agreed deadlines.

C.

Reducing quality testing in order to deliver within agreed deadlines.

Answers
D.

Favoring processes and tools over individuals and interactions.

D.

Favoring processes and tools over individuals and interactions.

Answers
Suggested answer: A

Explanation:

This approach aligns with Agile principles, emphasizing continuous improvement and effective workflow management, which can complement the structured framework of PRINCE2 Agile.

asked 03/12/2024
Knowledge Mathebula
35 questions

Question 10

Report
Export
Collapse

Which is consistent with the eight guidance points of PRINCE2 Agile?

A.

The project manager role is NOT required when incorporating IT-only frameworks.

A.

The project manager role is NOT required when incorporating IT-only frameworks.

Answers
B.

The project manager role is NOT defined by Scrum or Kanban.

B.

The project manager role is NOT defined by Scrum or Kanban.

Answers
C.

Working in an agile way removes the need for a project manager.

C.

Working in an agile way removes the need for a project manager.

Answers
D.

A project manager is indicative of a 'command and control' culture.

D.

A project manager is indicative of a 'command and control' culture.

Answers
Suggested answer: B

Explanation:

This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.

asked 03/12/2024
Ntombifuthi Shabangu
28 questions
Total 50 questions
Go to page: of 5