Question 21

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
Many Marketing Team members were expressing frustration that some members of the team had worked only on specific products and had not helped in the delivery of others. Therefore, the Marketing Team produced a Glad! Sad! Mad! board during a recent retrospective.
Which statement explains why this approach to identifying issues is appropriate for the 'controlling a stage' process?
Question 22

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
Nine timeboxes are scheduled for the marketing work.
Which baseline product is MOST relevant for defining which marketing product will be released in each timebox?
Question 23

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
When contributing to the development of the communication management approach, the Marketing Team felt that the only applicable agile technique to be included in the approach was the use of daily stand-ups.
Which reason BEST explains whether this is a suitable entry for 'tools and techniques' in the communication management approach?
Question 24

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The project manager has agreed that the 'Mission Control' room will have an issue register on the wall for project issues and all teams will display their own issue register on their own team wall as well.
Which BEST explains if this approach is suitable?
Question 25

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Website team manager has identified the need for a supplier representative to work on the social media website.
Who can fulfil this need according to the 'defined roles and responsibilities' principle?
Question 26

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Apps and Social Media work package includes the following requirements:
1. Fitness app - Must Have
2. Healthy eating app - Should Have
The burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.
The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.
What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?
Question 27

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Scrum Master has been advised by the supplier subject matter expert that the five day task of building the social media website is now almost complete - there is just one more day's work to do.
How should this be shown on the burn-down chart?
Question 28

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager is creating the stage plan for Stage 3. The project manager is trying to incorporate the Team Registration work package into the stage plan.
How should the stage plan be produced?
Question 29

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager has asked the Scrum Master who will be leading the website work stream to act as team manager. The team manager will act as a single point of contact for the project manager, taking on the responsibilities of a team manager. The team manager will continue to coach and lead the Website Team.
Which BEST describes how this tailors the organization theme?
Question 30

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project has been set up with multiple teams - one for each area of delivery. Each team has its own team manager.
The LGA employee who is an expert in health has been appointed to act as customer representative to all four of the delivery teams.
What BEST explains how this approach tailors the organization theme?
Question